3 Installation

3.1

Delivery, Transportation and Storage

3.1.1

Receipt of the UPS and visual inspection

Upon receiving the UPS, carefully examine the packing container and the UPS for any sign of physical
damage. In case of damage, notify immediately the carrier.
The packing container of the UPS protects it from mechanical and environmental damage. To increase
its protection, the UPS is wrapped with a plastic sheet. Preserve the packaging for later re-use.
3.1.2

Unpacking

After examining the package, remove the foam and the plastic cover. Ensure that the received UPS
corresponds to the material indicated in the delivery note.
3.1.3

Storage of UPS

If you plan to store the UPS prior to use, keep it in a dry, clean and cool storage room with an ambient
temperature between (-15 °C to +60°C) and humidity of less than 95% non-condensing. If the packing
container is removed protect the UPS from dust.
Keep the UPS always in upright position and do not drop the equipment.
3.2

Site Planning and Positioning

3.2.1

Planning before the installation

The appropriate place of installation for the unit is to be selected in such a way that the danger of
damage to the UPS is minimized and a long service life of the device is thus ensured. Please observe
the following instructions:
- Install the UPS in the indoor area.
- Leave 25 cm of space on each side of the cabinet to enable cooling airflow and to ensure that the
circulation of air to the ventilation slits is not obstructed.
- Avoid excessively high temperature and excessive moisture.
3.3

General Characteristics

3.3.1

Front View

1kVA
2-3 kVA
Figure 1: Front View 1-3kVA
04-3598_ABB_PVA11_T_1-3kVA_EN_REV-B.doc
Modifications reserved
Page 10/29 ABB