3 I N S TA L L AT I O N

3 .2 Site planning and positioning

3 .2 .1 Planning before the installation

3.2.1-1:
To ensure a long service life, install the unit
Step 1
in a position where any danger to the UPS
3.2.1-2:
is minimized:
Step 2
• Install the UPS indoors.
3.2.1-3:
• Leave 50 cm of space on each side of the
Step 3
cabinet to allow cooling airflow and ensure
that the circulation of air to the ventilation
slits is not obstructed.
• Avoid excessively high temperatures and
excessive moisture.
• Make sure that the surface is solid and flat.

3 .2 .2 Preparation

For safety consideration, the UPS is shipped out
from the factory without connecting battery
wires. Before installing the UPS, please follow the
steps below to re-connect the battery wires first.
Step 1. Remove the front panel. (figure 3.2.1-1)
Step 2. Re-connect the battery wires.
(figure 3.2.1-2)
Step 3. Put the front panel back on the unit.
(figure 3.2.1-3)

3 .2 .3 Positioning

The PowerValue 11 RT G2 can be mounted in a rack
or installed in a stand-alone configuration.
WARNING
WATER CONDENSATION MAY OCCUR IF
THE UPS IS UNPACKED IN A VERY LOW
TEMPERATURE. TO AVOID HAZARDS AND
RISK OF ELECTRIC SHOCK, WAIT UNTIL
THE UPS IS FULLY DRY BOTH INSIDE AND
OUTSIDE BEFORE INSTALLING/USING
THE UPS.
1
2
3.2.1-1
3.2.1-2
2
3.2.1-3
11
1