Commissioning
If after several seconds the inverter does not show any activity on the display, verify that the specified polarities
have been followed for the connection of the batteries and/or the PV array.

17.2.1. Configuring the unit for the first time

The first time that the inverter is powered from the batteries or the PV array, it must be configured to operate
correctly.
These units can be used in different types of installations. The configuration of the unit is different depending on
the type of installation where the inverter is to be used.
INFO
For the first configuration and start up of the unit, visit
www.ingeconsuntraining.info/?page_id=13069..
In the APPLICATIONS section, enter the type of installation and download the corresponding
installation and configuration document. For a correct start-up of the unit, follow the
instructions given in this document.