INGECON SUN STORAGE 1PLAY TL M Technical guide for installations with INGECON SUN STORAGE 1Play TL M Ingeteam Power Technology S. A. Technical Guide...
The ISS 1Play TL M inverter doesn´t allow for active poles (positive or negative) to be grounded in PV panels or batteries. It is compatible with TT and TN grounding system. Figure 1: INGECON SUN STORAGE 1Play TL M Technical Guide...
External wattmeter. Check the “List of approved Power Meter for ISS 1Play TL M”, available in the Ingeteam webpage. (In case of use the internal wattmeter of the inverter, consult the “Installation and Operation Manual” of ISS 1Play TL M, available in the Ingeteam webpage).
Page 5
INGECON SUN STORAGE 1Play TL M Figure 2: Self-consumption installation Operating mode The EMS of the ISS 1Play TL M manages the energy flows in the installation in line with the following principles: • If the grid is available, it operates in the same manner as a self-consumption installation: Photovoltaic energy is used as a priority to supply loads and to charge the battery.
Although the INGECON SUN STORAGE 1Play TL M provides an extra current during load connection transients such as motors, INGETEAM recommends the use of frequency drives with this type of load for the installation to work properly in UPS mode.
Page 7
INGECON SUN STORAGE 1Play TL M Figure 3: UPS installation Operating mode The ISS 1Play TL M manages the energy flows in the installation in line with the following principles: • When the grid is operational, the priority is to keep the batteries fully charged SOC Grid so that they can be used as back-up when required.
Although the INGECON SUN STORAGE 1Play TL M provides an extra current during load connection transients such as motors, INGETEAM recommends the use of frequency drives with this type of load to avoid transient voltage drops (2-3 seconds) during their connection.
Page 9
INGECON SUN STORAGE 1Play TL M Operating mode The ISS 1Play TL M manages the energy flows in the installation in line with the following principles: • Photovoltaic energy is used as a priority to supply loads and to charge the battery.
INGECON SUN STORAGE 1Play TL M 3 Attachment I. Links Detailed wiring diagrams and further information about the operation modes can be downloaded at the following link: https://www.ingeconsuntraining.info/?page_id=25439 Technical Guide 04/06/2021 10/10...