Mounting the tiles

Install the tiles in the array row by row. Do not attempt to construct the array column by column.
Warning! If not avoided, the following could result in death or serious injury.
External support for a display wall must be designed and implemented by a Christie qualified
installer and must comply with local area regulations and safety standards.
All display walls must have permanent external supports. The amount of external support
required depends on the size of the display wall.
A minimum of two people or appropriately rated lift equipment is required to safely lift, install,
or move the product.
1. If present, remove the metal plates that cover all the external pass-through holes in the tile
chassis.
2. Place the tile face down on a protected surface and remove the rear cover.
3. Loosen the four thumb screws on the back of the carrier assembly (A).
The rear thumb screws secure the carrier assembly to the tile chassis. Leave the rear thumb
screws loose to allow the carrier assembly to be removed from the front.
4. Reinstall the rear cover.
5. Using the magnetic tool, remove the LED modules from each corner of the tile and set them on
a padded surface.
Make note of the carrier assembly that the LED module came from, and ensure it is reinstalled
on the same carrier assembly and in the same position on the carrier assembly.
6. Loosen the four thumb screws, one in each corner of the tile (B).
Velvet LED Display System Installation and Setup Guide–Apex A2L Series
020-102873-01 Rev. 1 (06-2018)
Copyright
2018 Christie Digital Systems USA, Inc. All rights reserved.
©
Installation and setup
20

Advertisement

Table of Contents
loading

Table of Contents