Powering on the array

Turn on each component in the array in the order below.
1. Start the computer that is the video source.
2. Turn on each rectifier in the Remote Power Supply Rack Shelf.
When a rectifier is on, the OFF and ON buttons are flush with the front plate (A). When a
rectifier is off, the ON side of the switch extends beyond the front plate (B).
As the wall is powering on, light flickers on the tiles.
3. Turn on the controller.
a) On the rear of the controller, turn the power switch to On.
b) On the front of the controller, press the Power button.

Powering off the array

Turn off each component in the array in the order below.
1. Turn off the controller.
a) On the front of the controller, press the Power button.
b) On the rear of the controller, turn the power switch to Off.
2. Wait for 3-5 minutes after powering off the controller.
3. Turn off each rectifier in the Remote Power Supply Rack Shelf.
Velvet LED Display System Installation and Setup Guide–Apex A2L Series
020-102873-01 Rev. 1 (06-2018)