CHAPTER 3: INSTALLATION
3.2

PRE-INSTALLATION CHECKOUT

The SEHI is equipped with an NVRAM reset switch (Figure 3-1) located
behind the grillwork on the side of the hub. Ensure that this switch is in
the DOWN position by looking in through the grillwork on the right side
of the hub. If the switch is UP, move it into the DOWN position with a
non-metallic tool. Do not remove the chassis cover to perform this
operation. Leaving the switch in the UP position results in user-installed
parameters such as IP address and Community Names being cleared from
NVRAM whenever the SEHI loses power and/or is reset. See Chapter 5,
Section 5.4 for detailed instructions on setting the NVRAM switch.
3.3

INSTALLING THE SEHI

The SEHI may be installed on a tabletop or shelf, or in a 19-inch rack, and
configured as a standalone or stacked hub.
Refer to Section 3.3.1 for information concerning a tabletop or shelf
installation. Section 3.3.2 describes the rackmount installation.
3-2
NVRAM Switch located behind grating
Figure 3-1. NVRAM Switch Location
Rear of Chassis
1490_5
SEHI USER'S GUIDE