Procedure
Step 1 Cut the feeder cable, as shown in Figure 5-90.
Figure 5-90 Cutting a feeder cable (unit: mm)
Step 2 Use a brush to remove the dirt on the cross-section of the feeder cable.
Step 3 Feed the feeder cable into the heat-shrink tubing, and cover the outer conductor of the feeder
cable with the O-ring seal, as shown in Figure 5-91.
Issue 01 (2017-12-29)
Ensure that the feeder cable is cut with reference to the guide in the package box of the
connector.
After you cut the feeder cable, ensure that the cross-section of the outer conductor is
smooth, intact, and round.
Ensure that the feeder cable is cut at the wave crest of the outer conductor.
The inner conductor must be beveled, as shown in Figure 5-90.