Power cord connection:
1. Unlock and open the electrical enclosure
door.
2. Insert a strain relief fitting into an open hole
at the bottom of the electrical cabinet to grip
the power cord (supplied by customer) and
route a power cord into the cabinet to the
top of the terminal strip at the upper right
side of the cabinet (XT1).
3. Connect the three power wires terminals L1,
L2, & L3. Connect the ground wire (typically
green) to the PE terminal.
4. Check that the power cord is routed inside
the cabinet so as to avoid contact with other
components inside the cabinet.
Check for correct rotation of the motor
1. Close the electrical enclosure door.
2. With power connected and the main
disconnect turned ON, the power light on the control panel will be lit.
3. Place the Stroke switch in the JOG position.
4. Press the motor start button and listen for the sound of the hydraulic pump pumping fluid.
Check that the rotation direction of the motor is in accordance with the indication of the
nameplate of oil pump. If not, change it at once. In case air is found in the hydraulic system,
push the buttons for motor starting and stopping alternatively until the air is discharged.
Recheck the hydraulic oil level.
5. Press the foot pedal. The clamping cylinders should extend, and the blade beam should
move down. If not, disconnect power to the machine, and switch the L1 and L3 wires. DO
NOT move the ground wire.