ID61/62 Series Panel - Installation, Commissioning & Configuration Manual
997-457-000-8, Issue 8
January 2010
4

Commissioning

4.1 Introduction

This section describes how to bring the ID61/62 Series
Panel into an operational state (commissioning) ready
for configuration. To commission this series of panels
follow the steps detailed below. Information on how to
configure the panel is given in Section 5, Configuration.
1 Check that the panel is installed and assembled
correctly, refer to Section 4.2, Preliminary Checks.
2 Check internal panel configuration, Section 4.3,
Internal Checks.
3 Check and connect the external wiring, refer to
Section 4.4, External Wiring Checks.
4 Configure the panel for the particular system
requirements, refer to Section 5, Configuration.
5 Check that the system is working correctly.

4.2 Preliminary Checks

Before connecting the mains power to the panel, check
that:
a. All PCBs are correctly fitted.
b. All internal wiring is correctly connected.
c. The loop wiring and external sounder circuits have
NOT, at this stage, been connected to the Main PCB.
d. Check that there are no more than 10 CLIP device
addresses on a mixed-protocol loop. Be aware that
multi-criteria sensors and some modules, e.g.M720,
M721 use more than one loop address - the first device
address taken up is OPAL, the others are CLIP so an
M721 module uses one OAL and two CLIP addresses.
e. The appropriate end-of-line devices are connected to
the sounder outputs. For backwards compatibility, the
default is set for 6k8 resistor end-of-line devices.
However, an option is provided to select diode end-
of-line devices to meet the requirements of EN54-13,
which requires the ability to monitor for partial-open
and partial-short circuit faults. A diode is provided for
each sounder circuit should this option be selected.
f. The 150R termination resistors are connected to the
first and the last panels on the RS485
Communications Link.
22