Dangers During Commissioning - RMG TME400-VM VMF Series Operating Manual

Turbine meter
Hide thumbs Also See for TME400-VM VMF Series:
Table of Contents

Advertisement

1 Introduction
Observe the following, in particular:
• Changes to the TME400 are not permitted.
• The technical specifications must be observed and followed for safe operation.
Performance limits must not be exceeded (chapter 5 Technical data).
• For safe operation, the TME400 must only be used in the scope of the in-
6
tended use (chapter 1.3 Overview of versions).
• The TME400 complies with current standards and regulations. However, dan-
ger can arise with misuse.
1.2.4.2.
Initial commissioning
Note
An acceptance test certificate must be created during the commissioning.
This, the operating manual and the EU Declaration of Conformity must be
stored so that they are always readily available.
All sharp edges on the device were removed, insofar as possible. However,
personal protective equipment provided by the operator must be worn during
all work.
Danger
Install the device as specified in the operating manual. If the device is not in-
stalled as specified in the operating manual, there may be a risk that ade-
quate explosion protection is not provided.
The explosion protection is lost!
Manual TME400-VMF · EN07 · December, 7

Dangers during commissioning

The initial commissioning must only be carried out by
specially trained personnel (training by RMG) or RMG
service personnel.
th
2020

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Tme400-vmTme400-vmf

Table of Contents