Connect The Control Cable For The Tilt Sensors From The External Customer Interface To The Charge Post (Option) - ABB Terra HP Generation 3 CE Instruction Manual

175 kw static dc system
Table of Contents

Advertisement

Electrical installation of the charge post
Procedure
1. Guide the cable (A) to the switch
ethernet device (B).
2. Connect the RJ45 plug to the switch
port X1 (C).
8.8
Connect the control cable for the tilt sensors from the
external customer interface to the charge post (option)
Preliminary requirements
Procedure
1. Strip the insulation from the ends
of the wires (A) to (D). For the
specification, refer to section 12.19.7.
2. Crimp ferrules onto the end of the
wires.
3. Loosen the screws of the terminal
block X-20.
4. Connect these wires:
5. Tighten the screws to the correct torque. For the specification, refer to section
12.14.
56
Torque screwdriver, cross
Wire cutter
Wire stripper pliers
Crimp pliers
V- wire (A), grey, to the terminal
X-20-4 (E)
V+ wire (B), blue, to the terminal
X-20-5 (F)
Rin wire (C), green, to the terminal
X-20-6 (G)
Rout wire (D), brown, to the terminal X-20-7 (H)
C
Control cable for the tilt
sensors. Refer to section
12.19.7.
Ferrules
D
C
B
A
9AKK107992A2254-EN | 005
B
A
H F E G

Advertisement

Table of Contents
loading

Table of Contents