10) Move the remote control lever between
forward and reverse positions at the
first station several times and place the
shift rack in the junction unit in neutral.
Check if the grooves on the rack and
cable end are offset each other.
Repeat the check at the second station.
11) If still offset, repeat the above steps 4)
to 10) until the offset is eliminated.
12) Install the cable clamp, move the
remote control lever between forward
and reverse positions at the first station
several times and check that the volt-
age is within the specification.
13) Install the clamp covers and the side
cover.
10A-28