Operating Instructions GMK5250L
11.1 Rigging work checklists for crane operation with the main boom
10. Fold out all ladders and extend all stair treads;
à
Ladders , p. 4 - 5,
à
Step at the crane cab , p. 11 - 141.
11. Inspect the truck crane, while looking out in particular for any leaking
fluids (oil, fuel or water).
12. Start the engine for crane operation;
13. If necessary, switch off the houselock and unlock the superstructure;
à
Switching off the houselock , p. 10 - 19,
à
Unlocking the superstructure , p. 10 - 16
14. Pick up the hook block and reeve the hoist rope again, if necessary;
à
Hook block on a separate vehicle , p. 11 - 99,
à
Hook block on the bumper , p. 11 - 95,
à
Reeving and unreeving the hoist rope , p. 11 - 104.