Commissioning (basic settings)

10.
Commissioning (basic settings)
10.1.

End stops in part-turn actuator

Information
50
SQV 05.2
SQV 14.2 / SQRV 05.2
1.
Set selector switch to position 0 (OFF).
Information: The selector switch is not a mains switch. When positioned to 0
(OFF), the actuator cannot be operated. The controls' power supply is
maintained.
2.
Switch on the power supply.
Information: Observe heat-up time for ambient temperatures below 30 °C.
3.
Perform basic settings.
The internal end stops limit the swing angle. They protect the valve in case of limit
switching failure during motor operation and serve the purpose as limitation for
manual operation via handwheel. They may not be used for torque tripping in end
positions during standard operation.
End stop setting is generally performed by the valve manufacturer prior to installing
the valve into the pipework.
Exposed, rotating parts (discs/balls) at the valve!
Pinching and damage by valve or actuator.
End stops should be set by suitably qualified personnel only.
Never completely remove the setting screws [2] and [4] to avoid grease leakage.
Observe dimension T
The swing angle set in the factory is indicated on the name plate:
Figure 62: Example: Swing angle on name plate
The setting sequence depends on the valve:
-
Recommendation for butterfly valves: Set end stop CLOSED first.
-
Recommendation for ball valves: Set end stop OPEN first.