Set Up; Dig Approach Trench - Kubota RT120Q Operator's Manual

Table of Contents

Advertisement

Drill - 128

Set Up

EMERGENCY SHUTDOWN - Turn ignition switch to STOP.
To help avoid injury:
Comply with all utility notification regulations before digging or drilling.
Set up warning barriers and keep people away from machine and jobsite.
Do not operate drilling attachment if bore path is less than 10' (3 m) from any underground hazard.

Dig Approach Trench

1. Mark planned bore path and all located
utility lines with flags or paint.
2. Dig an approach trench (1) along the
intended bore path.
IMPORTANT: Ensure that approach
trench is:
deep enough for pipe to lay flat
and enter soil at correct angle,
at least 20' (6 m) long, and
at least 4" (100 mm) wide.
Jobsite hazards could cause death or serious injury. Use
correct equipment and work methods. Use and maintain proper safety
equipment.
Read operator's manual. Follow safety rules and know
how to use all controls. Your safety is at stake.
RT120Q Operator's Manual
273-475
Set Up