UPS5000-H-(400 kVA-600 kVA)
User Manual (100 kVA Power Module)
Figure 6-13 EPO NC connection
Figure 6-14 EPO NO connection

6.4 Verifying the Installation

You need to carefully check items 08 and 09 listed in the table. If the check results
of these two items do not meet the acceptance criteria, the UPS may be damaged.
Table 6-5 Check items and acceptance criteria
No.
01
02
03
Issue 01 (2020-11-30)
NO TE
● When you use the NC status, remove the jumper between EPO_NC and EPO_12V first.
When you turn off the EPO switch, EPO is triggered.
● When you use the NO status, ensure that the jumper is connected between EPO_NC and
EPO_12V. When you turn on the EPO switch, EPO is triggered.
NO TICE
Item
UPS installation
Neat arrangement
Layout of the busway
and cables
Copyright © Huawei Technologies Co., Ltd.
Acceptance Criteria
The UPS is securely installed and does not tilt
due to vibration.
The UPS and its adjacent cabinets are neatly
arranged and secured with connecting kits.
The busway and cables are routed properly as
required by the customer.
6 Installation
65