UPS5000-H-600 kVA-FTN
User Manual (Singapore, 100 kVA Power Modules)
Figure 4-67 Pre-routing parallel cables (using four parallel UPSs as an example)
----End
4.11 Verifying the Installation
You need to carefully check items 08 to 12 listed in the table. Otherwise, the UPS
may be damaged.
Table 4-11 Checklist
No.
01
02
03
04
Issue 02 (2023-11-07)
CA UTION
Check Item
Cabinet installation
Neat arrangement
Layout of the busway and
cables
Labels on the busway and
cables
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Installation and Cable Connection
Acceptance Criteria
The cabinets are securely installed and
do not tilt due to vibration.
The UPS and its adjacent cabinets are
neatly arranged and secured with
connecting kits.
The busway and cables are routed
properly as required by the customer.
Both ends of a busway and cable are
labeled. Labels are concise and easy to
understand.
113