Step 2 Tap Start on the right of Shallow Dis. Test to start a shallow discharge test.
Figure 7-10 Starting a shallow discharge test
----End

7.6.1.3 Performing a Capacity Test

Context
Before performing a capacity test, ensure that:
● The UPS is working in normal mode; float charging or hibernation has lasted
● The UPS generates no battery overtemperature, overvoltage, or overcurrent
● The mains, batteries, charger, and discharger are normal. No overload alarm is
Procedure
Step 1 On the home screen of the LCD, choose System Info > Maintenance > Battery
Maint.
Issue 01 (2020-11-30)
NO TE
When the battery test is completed normally, the test data is used as common test data.
Record the data obtained from the latest five tests.
The shallow discharge test automatically stops in any of the following cases:
● The battery discharge capacity reaches the specified value (10%–50%, 20% by default).
● The discharge voltage reaches the warning threshold (calculated in real time).
● The load rate fluctuation exceeds 10%.
● An alarm is generated.
NO TICE
for 2 hours after the SOC reaches 100%; the load rate fluctuation is less than
10%.
alarm. No generator is connected to the UPS.
generated.
Copyright © Huawei Technologies Co., Ltd.
7 System Commissioning