2. INSTALLATION

Do not connect the equipment to the mains before the installation is complete.
Do not modify the welding equipment in any way, except for the changes and adjustments covered in the man-
ufacturer's instructions.
Do not attempt to move or hang the equipment mechanically (e.g. with a hoist) from the handle on the power source
unit or on the wire feeder unit. The handles are for manual moving only.
When installing the full set of equipment stacked as a tower – water cooler at the bottom, power source in the middle
and wire feeder at the top – always install and secure the equipment onto a Kemppi cart compatible with X5 FastMig
or secure the equipment to other adequate support on site.
When installing the full set of equipment stacked as a tower and using the double wire feeder rotating plate or coun-
terbalance arm, always use the broader front roller support plate delivered with the equipment. This applies to the 4
wheel cart.
Place the machine on a horizontal, stable and clean ground. Protect the machine from rain and direct sunshine. Check
that there is enough space for cooling air circulation in the machine vicinity.