MAINTENANCE INSTRUCTIONS

Loader Installation

1. Connect P port of the loader hydraulic distributor to the line on the tractor marked P (from the PTO valve).
2. Connect the T port of the loader hydraulic distributor to the line marked T on the tractor.
3. Connect the remaining line from the hydraulic distributor to the line marked P1 (to the transmission case)
on the tractor.

Loader Disconnection (Loader Valve or Loader Port)

1. Disconnect the loader hydraulic hoses.
2. Install the cap (PF3 / 8) on the pipe (PF3 / 8).
1 - Loader Selective Valve
When installing the loader, the selective valve must point up.
If the loader is not installed, the valve must point to the left.