Section 3 - Installing Wall Frames - Thermo Scientific FISHER HAMILTON MAX/WALL Installation Manual

Technical wall system
Table of Contents

Advertisement

MAX/Wall
Technical Wall System
®
Section 3 – Installing Wall Frames
3.1
Overview of Anchoring the
Walls to the Ceiling
1. Determine where the wall frames will be located
on the floor. Mark the center lines of the assem-
blies.
2. Use a plumb line to transfer the center line loca-
tions to the ceiling.
3. Fasten the ceiling channels to the ceiling.
a) If the ceiling is structural, channel may
be mounted directly to the ceiling.
b) If the ceiling is suspended, it will require
reinforcement channels to be installed above
the ceiling tiles to support the ceiling channel.
Reinforcement channels must be oriented at
a right angle to the ceiling channel and lay
between ribs of suspended "T" grid system.
See Figure 3-1.
Figure 3-1 Detail showing normal
installation - Ceiling Reinforcement
Channel between T-Grid System
24" Ceiling Reinforcement Channel
Figure 3-1 Detail showing normal
installation - Ceiling Reinforcement
Channel directly above T-Grid channel
24" Ceiling Reinforcement Channel
Figure 3-1 Detail showing optional installation
- Ceiling Reinforcement Channel with Field-Cut
slot and additional T-Grid channel
16
24" Ceiling Reinforcement Channel
Ceiling Channel
Ceiling Channel
Factory-Cut Slot
Ceiling Channel
Suspended
Ceiling Tiles
Ceiling
Channel
Factory-Cut Slot
Ceiling Extension
Factory-Cut Slot
T-Grid
Ceiling Extension
Field-Cut Slot to engage 8" grid
12"
8"
Ceiling Extension
Figure 3-1 Attaching MAX/Wall
to Ceiling Grid
Lay-In Ceiling Tile
T-Grid
Lay-In Ceiling Tile
4"
T-Grid
Lay-In Ceiling Tile
Ceiling
Reinforcement
Channels