Large Capacity Start Up Control (Heating)

For startup, oil return operation, or setup after defrosting, start up multiple compressors at a high speed according to the
conditions of indoor units with thermostat ON, thus maximizing the equipment capacity.
25
20
15
Pressure
10
5
0
[Starting conditions]
[Control]
1. Start multiple INV compressors in the system at one time.
2. Start multiple STD compressors in the system at intervals of 15 seconds.
Function
Time
Start up STD compressors at intervals of 15 seconds.
The system starts heating operation with thermostat ON at a high load.
The system completes defrosting operation.
OR
The system switches the operation mode from cooling to heating or
simultaneous cooling and heating operation.
Special Control
INV
STD
Pc
9
8
Number of
7
compressors
6
5
Pe
4
3