Preparing The Sub-Base - Festo VIFB11-02 Series Manual

Valve terminal/valve sensor terminal with field bus connection
Table of Contents

Advertisement

VIFB11 - 02
5/3
Connections
for common
lines
1
3/5
Connection
Procedure of preparing the sub-base
• Remove adhesive foil as late as possible (to avoid dirt)
Unilateral
• Fit blind plugs unilaterally
• Remove adhesive foil as late as possible (to avoid dirt)
Bilateral
Fig. 4/3: Connections on the sub-base
4-8
4. Installation

Preparing the sub-base

Connections for common lines are provided on
both sides of the sub-base. The common lines
can therefore be fitted on the left or the right,
depending on individual requirements. To in-
crease the air flow, we recommend that the
lines for compressed air supply and ventilation
be connected on both sides in the following
cases:
when the valve terminal/valve sensor termi-
nal has more than 10 valves (rated supply
pressure 6 bar).
with large volume actuators
The connections should be made in accord-
ance with the table below.
Connections
for common
lines
Blind plugs
(to be ordered
separately)
9902d