3.3 Layout Requirements

3.3.1 Indoor Unit Space Requirements

Equipment Room Requirements
Installation Space
Issue 05 (2019-12-20)
To ensure that the environment control system in the smart cooling product room works
properly, take moisture-proof and thermal insulation measures.
The equipment room should have good heat insulation, and the walls and floor should be
protected against moisture. The moisture-proof layer of the ceiling and wall must be
made of polyethylene film. The paint on the concrete wall and floor must be
moisture-proof.
Incoming outdoor air may increase the load of system heating, cooling, humidification,
and dehumidification. Therefore, it is recommended that outdoor air be prevented from
entering the equipment room. (The incoming outdoor air should be less than 5% of the
entire indoor airflow. All doors and windows should be closed and the gap should be
minimal.)
To ensure the normal operation of the indoor unit, select a spacious space for installing
the indoor unit.
Do not install the indoor unit in a narrow place. Otherwise, the airflow will be blocked,
the cooling period will be shortened, the supply and return air will mix up, and air noise
will be caused.
To ensure good ventilation, do not place the smart cooling product in the corner of a
room or at the end of a long and narrow room.
To facilitate the normal maintenance of the indoor unit, do not install other devices
above the indoor unit.
Copyright © Huawei Technologies Co., Ltd.
3 Installation Guide
33

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netcol500-a022

Table of Contents