Table 4. Stand-alone gateway installation checklist (continued)
Task
Description
U
2–1
Have the customer suspend all I/O activity.
h
Power-off any components that are
powered-on, and shut down power to the
frames.
2–2
Install the server.
h
2–3a
If the customer purchased a new TSSC and
h
TSSC Ethernet switch and has not yet installed
them, do so now then go to task 3-1.
2–3b
If the customer has an existing TSSC (with FC
h
2719) and TSSC Ethernet switch, that can be
used with the gateway, go to task 3-1.
Section 3: Apply cable labels and make cable connections
3–1
Label and connect the power cords on the
h
server to the PDU.
If you installed a TSSC, label and connect the
3–2
h
power cable on the TSSC to the PDU.
3–3
If you installed a TSSC Ethernet switch, label
h
and connect the power cable on the switch to
the PDU.
3–4
Label and connect an Ethernet cable from the
h
server to the TSSC's Ethernet switch.
3–5
Label and connect an Ethernet cable from the
h
server to the customer's LAN.
3–6
Label and connect Ethernet cables from the
h
server to the customer's replication network, if
applicable.
3–7
Label and connect an Ethernet cable from the
h
RSA on the server to the TSSC's Ethernet
switch.
3–8
Label and connect an Ethernet cable from disk
h
controllers A and B, to the TSSC's Ethernet
switch.
Label and connect an Ethernet cable from the
3–9
h
TSSC's external port (Eth2) to the customer's
LAN.
3–10
Label and connect fibre channel cables from
h
the server to disk controllers A and B.
3–11
Label and connect fibre channel cables from
h
the server to the customer's host network.
Section 4: Power-up all components
4–1
Turn on the breaker(s) to power the PDUs.
h
4–2
Power-up the disk expansion module(s).
h
4–3
Power-up the disk controller.
h
4–4
Power-up the server.
h
Power-up the TSSC, display panel, and TSSC
4–5
h
Ethernet switch
Section 5: Perform post-installation validation checks
Where to find information
Refer to the component-specific documentation
for power-off instructions.
"Installing the server" on page 22.
The TSSC Maintenance Information (MI),
provided on the IBM System Storage TS7650
with ProtecTIER Publications CD.
N/A
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
"Cabling a stand-alone gateway" on page 27.
N/A
"Disk expansion modules" on page 39.
"Disk controllers" on page 39.
"Servers" on page 39.
"TSSC, display panel, and TSSC Ethernet
Switch" on page 40.
Chapter 4. Installing the TS7650G hardware
17