Section 7
IEC 61850 communication engineering
146
When a changed configuration is written to the protection relay, the horizontal
communication configuration needs to be updated.
GUID-EEB7D9BD-5D8C-4A18-9A94-848B2821658D V2 EN
Figure 96:
Updating the communication configuration in the IED with the
configuration made in PCM600
1.
Select which configuration part to include in writing.
Select GOOSE to update the GOOSE configuration part in the IED.
Select Process bus (IEC 61850-9-2) to update the IEC 61850-9-2
configuration part in the IED.
2.
Select whether or not to update the configuration.
Click Continue to update the selected communication configuration part(s) in
the IED. The options can be left unselected. In this case, other parts of the
configuration are updated.
Click Cancel to cancel the whole writing operation.