Upload calibration values to the i-Vu® application
CAUTION If your system has an i-Vu® user interface, you must run the Test and Balance report in the i-Vu®
application after using VAV Zone II. Running the report uploads the values from the controller to the i-Vu®
application. You will lose all your calibrations if you download to the controller in the i-Vu® interface before
running this report.
In the i-Vu® interface, select the top level in the navigation tree.
1
Click Reports > Commissioning > Test and Balance.
2
On the View tab, click Run.
3
Go to Step 4: Run a report (Optional).

Run a report in VAV Zone II (Optional)

After balancing, you can run a report (.htm file) in Test & Balance that shows each controller's calibrated values
and design values. You can view or edit the file in Microsoft Excel, Microsoft Word, or any web browser.
Select Session > Report.
1
Select an existing report or type a name in the File Name field.
2
Click Save.
3
If you chose an existing report in step 2, select Append to add to the report or Overwrite to replace the report.
4
VAV Zone II Controllers
Installation and Start-up Guide
Action
Forces the damper to its maximum cooling position. Calibration fields apply only if the
primary use of this damper is cooling.
Forces the damper to its minimum occupied position and enables the Occupied Min
Flow calibration fields.
Forces the damper to its full closed position.
Forces the damper to its maximum heating position. Calibration fields apply only if
the primary use of the damper is heating.
Returns control of the damper to the control program. You must perform this step
when you finish test and balance.