Configuring ZS Sensors

The VAV Zone II automatically detects 1 ZS temperature sensor set to address (1). This sensor is labeled Main ZS
Sensor.
You must configure the ZS Sensor properties in the i-Vu® application or Field Assistant as follows:
Add more ZS temperature, humidity, or CO
Configuration section. Ctrl+click on the property name to open the microblock popup and configure the
settings on the Details tab.
NOTE See Service Configuration (page 81) for details.
Configuring the ZS Sensor Binder, and then the following as needed:
ZS Zone Temp
ZS Zone Humidity
ZS Zone CO2
ZS model to show on graphic
Configure Setpoint Adjustment. See Setpoints (page 73).
Set Occupancy and Override properties. See Maintenance (page 89) for details.
Alarm and Maintenance indications on the ZS Pro (display model) sensors. See Appendix C: ZS Sensor
display for VAV Zone II (page 100).

Performing system checkout

Verify that all power and communication connections are correct and tight.
1
Verify that all zone terminals, ductwork, and zone controllers are properly installed and set according to
2
installation instructions and job requirements.
Verify that all air duct connections are tight.
3
Verify that zone terminal fans and system controls operate properly. Verify that actuator screws are properly
4
tightened.
At the zone terminals, check electrical system and connections of any optional electric reheat coil. If hot
5
water reheat is used, check piping and valves against job drawings.
Verify that all zone terminal dampers are fully open.
6
If using an air source with field-installed controls, make sure controls and sensors have been installed and
7
wired per manufacturer installation instructions.
Verify that the air source motor starter and, if applicable, the Hand/Off/Auto (HOA) switch are installed and
8
wired.
Verify that the area around the air source is clear of construction dirt and debris.
9
10 Verify that final filters are installed in the air handler(s). Dust and debris can adversely affect system
operation.
VAV Zone II Controllers
Installation and Start-up Guide
2
sensors in the Properties > Control Program tab > Service
41
Start-up
CARRIER CORPORATION ©2019
All rights reserved

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents