Guide for any server or equipment you plan to install in the rack for additional site
preparation requirements.
Before installing Exalogic machines, perform the following tasks:
Thoroughly clean and vacuum the area in preparation for the installation.
1.
Note any problems or peculiarities at the site that require special equipment.
2.
Verify that the installation site flooring has a high enough strength rating to
3.
withstand the combined weight of an Exalogic machine and any installed
equipment.
Install all necessary electrical equipment and ensure that sufficient power is
4.
provided.
Refer to the Sun Rack II Power Distribution Units User's Guide for the power
requirements of the Sun Rack II power distribution units (PDUs).
Ensure that the installation site provides adequate air conditioning.
5.
Operate the air conditioning system for 48 hours to bring the room to the
6.
appropriate temperature.

2.4 Observing the Safety Guidelines and Warnings

Before installing the Exalogic machine, or installing any server or equipment into the
rack, read the Important Safety Information for Sun Hardware Systems document
included with the rack.
Observe all safety notices printed on the packaging and listed in the Sun Rack II
Safety and Compliance Guide and the Sun Rack II Power Distribution Units Users
Guide. Go to http://docs.sun.com to download these guides.
Note:
Contact your service representative to confirm that your equipment is qualified
for installation and use in an Exalogic machine. Oracle is not liable for any
issues when you install or use non-qualified equipment.
Observing the Safety Guidelines and Warnings
Chapter 2
2-3