5 Installation
5. Insert the optical fibers from below through the cable gland
into the splice box.
6. Mount the subscriber connectors on the optical fibers.
7. Plug the subscriber connectors into the SC-P plugs in the splice box.
8. Coil the residual glass fiber in the fiber reservoir. Observe the
permissible bend radii.
9. Screw on the enclosure of the splice box.
10. Reinstall the splice box on the top-hat rail.
11. Attach the optical fibers to the cable support rail using a cable tie. This ensures that the optical fibers cannot be
pulled out inadvertently.
12. Mount the panels (see Section 12.3.1.2, page 164).