Installation
The space in which the device is to be installed (including safety
distance) must be at least LxWxH: 1000 x 482.6 x 355.6 mm / 39.4 x
19 x 10.1 in (8HE)
If the fuel cell is installed within a sealed container, provide an
opening for supply air with an opening of at least 600 cm² / 95 in² –
at structured openings (fine grid, narrow gap), accordingly more.
The air openings of the installation space need to be protected
against the penetration of water and foreign particles (e.g. using
louvered metal sheets and fly screens).
Ensure that there is sufficient ventilation in the installation space to
prevent heat build-up. This can be done with additional openings or
an additional temperature-controlled fan.
Separation of air supply and off heat is necessary to prevent
recirculation of waste heat at high temperatures.
The electrical connections, the fill opening for EFOY Recovery Fluid
and the fuel cartridge must be easily accessible.
Install the device in an upright position only.
CAUTION!
Make sure that the device does not exceed the maximum inclination.
Inclination
Permanent: 10°
Temporary (<10 minutes): 35°