Installing Major Equipment; Installation Flow - Huawei iSiteC BTS3601C Installation Manual

Cdma base station
Hide thumbs Also See for iSiteC BTS3601C:
Table of Contents

Advertisement

Installation Manual
iSiteC BTS3601C CDMA Base Station
III. Note
When hoisting the BTS3601C, try to avoid any collision between BTS3601C and
l
the tower.
Distribute feeders along one side of the tower evenly and tidily. And all feeders
l
should be fixed via feeder dual-clips.
Install AC lightning protection box and grounding busbar on one support, and the
l
BTS3601C on the other. If the BTS3601C is cascaded with other BTS3601Cs,
install them on other supports.
Install PGND bar on the tower directly. And its location should be close (the PGND
l
cable length should not be more than 1m) to AC lightning protection box. It should
have its dedicated grounding downlead (made of 40mm % 4mm hot-gavanlizing
flat steel). PGND bar and its downlead should be connected via 35mm
yellow-green plastic insulation copper wire or welded directly. Neither the bar nor
the downlead should be insulated from the tower body.
The external shielding layer of BTS3601C coaxial feeder should be grounded on
l
tower top and grounded before the feeder is connected to the BTS3601C. The
grounding cable should be connected to the tower body. The grounding cable
should be made of yellow-green (or black) plastic insulation copper wire with the
core diameter not less than 6mm
Power cables and signal cables of BTS3601C should not be winded or bound on
l
the tower. They should be cabled as horizontally as possible.

2.3 Installing Major Equipment

2.3.1 Installation Flow

Figure 2-9 shows the flow to install BTS3601C major equipment:
2
.
2-13
Hardware Installation
2 Installing Cabinet Hardware