Installation Manual
iSiteC BTS3601C CDMA Base Station
The installation and maintenance of BSC cabinet should be done by 2 to 3
l
persons at best. The operations of leaning, tilting, and erecting the cabinet
should also be undertaken with the cooperation of 2 to 3 persons. Note that the
cabinet may fall down on account of the center of gravity when the tilt angle of
the center of gravity exceeds 10 degrees.
The process of laying down and erecting a cabinet is shown as Figure 7.
Figure 7 The process of laying down and erecting a cabinet
10.3 Sharp Edges
When conveying equipment by hand, please wear protective gloves to prevent cuts and injuries caused
by sharp edges.
Warning:
S-19
Safety Precautions