Airbridge BTS3606E&3606AE
System Commissioning Guide
1 Commissioning Preparations ..................................................................................................1-1
1.1 BTS Equipment.............................................................................................................................................1-2
1.2 Tools for Commissioning ..............................................................................................................................1-2
1.3 Personnel.......................................................................................................................................................1-2
1.4 Site Information ............................................................................................................................................1-2
1.5 Data Configuration Files ...............................................................................................................................1-3
2 Commissioning Modes .............................................................................................................2-1
2.1 Local Commissioning ...................................................................................................................................2-2
2.1.1 Local Commissioning in Telnet Mode .................................................................................................2-2
2.1.2 Reverse Maintenance ...........................................................................................................................2-2
2.1.3 Local Commissioning Tasks ................................................................................................................2-2
2.2 Remote Commissioning ................................................................................................................................2-2
2.2.1 Remote Commissiong on the LMT System .........................................................................................2-2
2.2.2 Remote Commissioning in Telnet Mode..............................................................................................2-3
2.2.3 Remote Commissioning Tasks .............................................................................................................2-3
3 Commissioning Process ............................................................................................................3-1
3.1 Commissioning Flowchart ............................................................................................................................3-2
3.2 BTS Startup Process......................................................................................................................................3-3
3.2.1 BTS Startup Flowchart.........................................................................................................................3-3
3.2.2 Description of the BTS Startup Process ...............................................................................................3-4
3.3 Starting Local Maintenance...........................................................................................................................3-7
3.3.1 Configuring the WS .............................................................................................................................3-7
3.3.2 Locally Logging In to the BTS in Telnet Mode .................................................................................3-10
3.3.3 Configuring the IP Address and Routing Information of the BTS ..................................................... 3-11
3.3.4 Starting the LMT................................................................................................................................3-12
3.3.5 Remotely Logging In to the BTS in Telnet Mode..............................................................................3-13
3.3.6 Performing the BSS Reverse Maintenance ........................................................................................3-14
3.3.7 Loading the BTS Software Locally....................................................................................................3-15
3.3.8 Loading the BTS Software Remotely ................................................................................................3-17
3.4 O&M Test....................................................................................................................................................3-18
3.4.1 Querying Basic Information of the BTS ............................................................................................3-18
Issue 02 (2006-10-10)
Huawei Technologies Proprietary
Contents
Contents
i

Advertisement

Table of Contents
loading

Summary of Contents for Huawei Airbridge BTS3606E

  • Page 1: Table Of Contents

    Airbridge BTS3606E&3606AE System Commissioning Guide Contents Contents 1 Commissioning Preparations ....................1-1 1.1 BTS Equipment.............................1-2 1.2 Tools for Commissioning ..........................1-2 1.3 Personnel...............................1-2 1.4 Site Information ............................1-2 1.5 Data Configuration Files ..........................1-3 2 Commissioning Modes ......................2-1 2.1 Local Commissioning ...........................2-2 2.1.1 Local Commissioning in Telnet Mode ....................2-2 2.1.2 Reverse Maintenance ...........................2-2...
  • Page 2 Airbridge BTS3606E&3606AE Contents System Commissioning Guide 3.4.2 Querying BTS Board Version ......................3-18 3.4.3 Verifying the Software Version ......................3-18 3.4.4 Querying Availability of BTS Cells ....................3-19 3.4.5 Querying Active Alarms of the BTS ....................3-19 3.4.6 Querying the Configuration Data of the BTS ..................3-19 3.4.7 Verifying the Consistency of the Configuration Data Between the BTS and the BSC Interface ..3-20...
  • Page 3 Airbridge BTS3606E&3606AE System Commissioning Guide Figures Figures Figure 3-1 BTS system commissioning flowchart .....................3-2 Figure 3-2 BTS startup flowchart........................3-3 Figure 3-3 Local connection properties......................3-8 Figure 3-4 Internet protocol (TCP/IP) properties ....................3-9 Figure 3-5 IP address of the WS used for local commissioning ...............3-10 Figure 3-6 Connection between the WS and the BCKM..................
  • Page 5 Airbridge BTS3606E&3606AE System Commissioning Guide Tables Tables Table 1-1 Tools for BTS commissioning ......................1-2 Table 3-1 Symptom of board initialization ......................3-4 Table 3-2 Indicator status during the OML setup ....................3-6 Table 3-3 Indicator status when the BTS downloads data configuration files............3-7 Table 3-4 Parameter associated with the forward power test................3-23...
  • Page 7: Commissioning Preparations

    Airbridge BTS3606E&3606AE System Commissioning Guide 1 Commissioning Preparations Commissioning Preparations About This Chapter The following table lists the contents of this chapter. Title Description 1.1 BTS Equipment Describes the BTS equipment to be verified before commissioning. 1.2 Tools for Commissioning Describes the tools involved in commissioning.
  • Page 8: Bts Equipment

    Optional DIN-male to N-female adapter Optional 1.3 Personnel Huawei technical support engineers and the engineers representing the customers complete the system commissioning together. The customer representative should sign the acceptance list after the commissioning is complete. 1.4 Site Information To facilitate the preparation of commissioning tools and commissioning schemes, collect the...
  • Page 9: Data Configuration Files

    Airbridge BTS3606E&3606AE System Commissioning Guide 1 Commissioning Preparations IP address for O&M PN code Service type 1.5 Data Configuration Files After making the data configuration files, the system commissioning personnel copies them into the workstation (WS). The system commissioning personnel must ensure that each data configuration file is named in the format of BTSXXX.txt.
  • Page 11: Commissioning Modes

    Airbridge BTS3606E&3606AE System Commissioning Guide 2 Commissioning Modes Commissioning Modes About This Chapter The following table lists the contents of this chapter. Title Description 2.1 Local Commissioning Describes typical operation tasks and classification of the BTS local commissioning. 2.2 Remote Commissioning Describes typical operation tasks and classification of the BTS remote commissioning.
  • Page 12: Local Commissioning

    Airbridge BTS3606E&3606AE 2 Commissioning Modes System Commissioning Guide 2.1 Local Commissioning The local commissioning is performed at the BTS site for the commissioning of the BTS3606E/3606AE or for the commissioning of the BSS. For the latter purpose, the coordination of the BSC is required.
  • Page 13: Remote Commissioning In Telnet Mode

    Airbridge BTS3606E&3606AE System Commissioning Guide 2 Commissioning Modes failed, timeout, and abnormal, and then sends the result to the LMT. In such a case, you can know the operation result. 2.2.2 Remote Commissioning in Telnet Mode In the case of remote commissioning in Telnet mode, you can log in to the BTS by using Telnet software.
  • Page 15: Commissioning Process

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Commissioning Process About This Chapter The following table lists the contents of this chapter. Title Description 3.1 Commissioning Flowchart Describes the BTS commissioning process and operation tasks in terms of flowchart. 3.2 BTS Startup Process Describes the general procedure for starting the BTS.
  • Page 16: Commissioning Flowchart

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide 3.1 Commissioning Flowchart Figure 3-1 shows the flowchart for BTS commissioning. Figure 3-1 BTS system commissioning flowchart Start Querying Basic Information of the Configuring the WS Logging In to the BTS in...
  • Page 17: Bts Startup Process

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process 3.2 BTS Startup Process This section describes the process of the BTS startup. 3.2.1 BTS Startup Flowchart Figure 3-2 shows the flowchart for BTS startup. Figure 3-2 BTS startup flowchart Start Initialize boards...
  • Page 18: Description Of The Bts Startup Process

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide For the descriptions of board indicators or module indicators, see the Airbridge BTS3606E CDMA Base Station Hardware Reference or the Airbridge BTS3606AE CDMA Base Station Hardware Reference. For the detailed information of BTS alarms, see the online help and the Airbridge BTS3606E&3606AE CDMA Base Station Site Maintenance Guide or the detailed alarm description...
  • Page 19 Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process If the OML cannot be set up during the BTS startup, the BTS restarts five minutes later. If the OML is interrupted when the BTS is processing services, the BTS sets up the OML repeatedly but the BTS do not restart.
  • Page 20: Table 3-2 Indicator Status During The Oml Setup

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Step 7 The BAM receives this request and sets up the OML from the BTS to the BAM. ----End In the case of setting up the OML in IP over FE mode, the IP address of the BCIM and the O&M IP address of the BTS cannot be obtained through the BOOTP if the BTS starts for the...
  • Page 21: Starting Local Maintenance

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Table 3-3 lists the indicator status when the BTS downloads data configuration files. Table 3-3 Indicator status when the BTS downloads data configuration files Observation Description Method Through the The board resets. After the boards run normally, the ACT indicator switches on.
  • Page 22: Figure 3-3 Local Connection Properties

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Prerequisites To configure the WS, ensure that: The WS is installed with the Windows operating system. The network adapter of the WS works normally. Operation Procedure The WS mentioned in the procedure is installed with Windows XP.
  • Page 23: Figure 3-4 Internet Protocol (Tcp/Ip) Properties

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Step 4 Choose Internet Protocol (TCP/IP) and click Properties. The Internet Protocol (TCP/IP) Properties dialog box is displayed, as shown in Figure 3-4. Figure 3-4 Internet protocol (TCP/IP) properties Step 5 In the General tab, choose Use the following IP address and set the IP address according to the following requirement.
  • Page 24: Locally Logging In To The Bts In Telnet Mode

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Figure 3-5 shows the IP address of the WS used for local commissioning. Figure 3-5 IP address of the WS used for local commissioning If the WS is used for remote commissioning, the IP address is set according to the requirement of the local network to which the WS belongs.
  • Page 25: Configuring The Ip Address And Routing Information Of The Bts

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Step 1 Use a crossover Ethernet cable to connect the Ethernet port of the WS and that of the BCKM. Figure 3-6 shows the connection between the WS and the BCKM. Figure 3-6 Connection between the WS and the BCKM...
  • Page 26: Starting The Lmt

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide The BTS is configured with the QC54BCIM. Operation Procedure To configure the IP address and routing information of the BTS locally, do as follows: Step 1 Log in to the BTS locally. See 3.3.2 "Locally Logging In to the BTS in Telnet Mode" for details.
  • Page 27: Remotely Logging In To The Bts In Telnet Mode

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Figure 3-7 User login dialog box Step 5 Click OK. If the login fails, the system reports the login failure. ----End 3.3.5 Remotely Logging In to the BTS in Telnet Mode Task Description Log in to a BTS remotely in Telnet mode.
  • Page 28: Performing The Bss Reverse Maintenance

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Step 1 On the service maintenance system, execute the command STR BTSTELPROXY to start the Telnet proxy for the BTS to be maintained. The duration of the Telnet proxy is defined in this step. If this duration expires, the Telnet proxy stops.
  • Page 29: Loading The Bts Software Locally

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process To connect the WS and the BCKM, connect a crossover Ethernet cable to the Ethernet ports on the WS and the BCKM. The IP address of the WS and that of the BCKM Ethernet interface must be in the same network segment.
  • Page 30 Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide The loading of the BTS software does not affect the service. The service is affected if you activate the BTS software. When using the FTP to load software, you can load only one software module by executing one command.
  • Page 31: Loading The Bts Software Remotely

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process 3.3.8 Loading the BTS Software Remotely Task Description Load the configuration files and BTS running software into the BTS from the LMT. Prerequisites Before starting the LMT, ensure that: The BAM server is operational.
  • Page 32: O&M Test

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide 3.4 O&M Test Unless otherwise specified, carry out the following tasks at the BAM side. Before the O&M test, ensure that the CCPM/CECM and the CMTR/OMTR works normally. 3.4.1 Querying Basic Information of the BTS...
  • Page 33: Querying Availability Of Bts Cells

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Step 1 Enter the following command: CHK CBTSSWVER Step 2 Click or press Enter. Step 3 Specify the values of the parameters. For example: CHK CBTSSWVER: BTSID=1; For the detailed explanation of the parameters, see the online help.
  • Page 34: Verifying The Consistency Of The Configuration Data Between The Bts And The Bsc Interface

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Step 3 Specify the values of the parameters. For detailed explanation of the parameters, see the online help. For example: DSP CBTSCFG: BTSNAME="BTS", BTSID=1, CFGID=CBTSINFO; Step 4 Click or press F9 to execute the command.
  • Page 35: Forward Power Test

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process When the BTS3606E/BTS3606AE uses the multi-carrier transceiver, the CMTR/OMTR and CMPA/OMPA need about five minutes to perform self adaptation after software loading. During this period, the index of transmit signals cannot satisfy the rated requirement and the adjacent channels are affected.
  • Page 36: Figure 3-8 Connection For Forward Power Test

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Figure 3-8 Connection for forward power test TX2/RX2 TX2/RX2 TEST CDDU TX1/RX1 TX1/RX1 - TEST cabinet top Power meter Antenna Step 2 In the Windows operating system of the LMT, select Start > Run, type Telnet xxx.xxx.xxx.xxx in the Run dialog box, and then press Enter to start Telnet.
  • Page 37: Forward Power Test Analysis

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Step 6 If the result is normal, conduct forward power interface tracing and compare the test result with the power test result. For example, to trace the CMTR or OMTR configured in slot 2, execute the following commands: HW CBTS>str infotrace...
  • Page 38 Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Parameter Description Obs chan power Channel power in the feedback Obs gain adjust Gain adjustment in the feedback Obs gain Identical Channel gain identical adjustment in the feedback IF gain adjust Adjustment of the intermediate frequency gain...
  • Page 39: Reverse Rssi Test

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process If Base band power is normal, but Digital power is not normal, the values of HPA Output power must be not normal in theory. In such a case, check the CMTR or OMTR to locate the fault.
  • Page 40: Reverse Rssi Test Analysis

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide Step 2 In the Windows operating system of the LMT, select Start > Run. Step 3 In the Run dialog box, type in Telnet xxx.xxx.xxx.xxx, and then press Enter to run the Telnet program.
  • Page 41: Service Function Test

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Parameter Description Revs pwr Reverse power RF AGC gain AGC gain of radio frequency Example of Test Result The following shows the RSSI value of the CMTR or OMTR configured in slot 2: HW CBTS>str infotrace : brdtp=trm,brdid=2,item="rssi"...
  • Page 42: Location Update Test

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide MS call test Handoff test Short message service test Mobile-originated packet data call test Mobile-terminated packet data call test 3.6.1 Location Update Test The test procedure is as follows: Step 1 Define a test MS in the HLR.
  • Page 43: Handoff Test

    Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Make a call from one MS to a PSTN subscriber and hook on after the conversation. Make a call from a PSTN subscriber to one MS and hook on after the conversation.
  • Page 44: Mobile-Originated Packet Data Call Test

    Airbridge BTS3606E&3606AE 3 Commissioning Process System Commissioning Guide 3.6.6 Mobile-Originated Packet Data Call Test Ensure that the system uses dynamic rate allocation. The test procedure is as follows: Step 1 Register a test MS in the HLR. Step 2 Prepare a BlueRose and keep an FTP server ready.
  • Page 45 Airbridge BTS3606E&3606AE System Commissioning Guide 3 Commissioning Process Status of Status of Status of MS Distance from the Adjacent Destination MS to the BTS Cell Sector 100% loaded 50% loaded Static Short 100% loaded 50% loaded Static Long 100% loaded...
  • Page 47: Troubleshooting

    Airbridge BTS3606E&3606AE System Commissioning Guide 4 Troubleshooting Troubleshooting About This Chapter The following table lists the contents of this chapter. Title Description 4.1 Overview of Briefs the troubleshooting during the BTS commissioning. Troubleshooting 4.2 Board Alarms Describes the types of board alarms and their handing methods.
  • Page 48: Overview Of Troubleshooting

    Airbridge BTS3606E&3606AE 4 Troubleshooting System Commissioning Guide 4.1 Overview of Troubleshooting The service commissioning includes the commissioning for the BSS, MSC/VLR, HLR, AUC, and the interfaces with the PSTN and internet. You must locate the fault by specific analysis. You can know the working status of the BTS by judging: Whether the MS can access to the network.
  • Page 49: Room Environment Alarms

    Airbridge BTS3606E&3606AE System Commissioning Guide 4 Troubleshooting To Handle Take the Following Action Power supply alarms, such as high Check that: voltage alarms, low voltage alarms, The PSU works normally. power failure alarms, and power fan The mains supply is normal.