Step 11: Complete the Installation Map

The Enphase Installation Map is a diagrammatic representation of the physical location of each
microinverter in your PV installation. You will create the virtual array in Enlighten from this map. Use the
blank map on page 40 to record microinverter placement for the system, or provide your own layout if a
larger or more intricate installation map is required.
You can build the system map manually, by peeling the serial number labels from the microinverters and
placing the labels on the installation map, or you can use the ArrayGun feature from the Enphase Installer
Toolkit to easily build and configure a system. Refer to
information.
To manually build the Installation Map:
a. Each Enphase Microinverter has a removable serial number label located on the mounting
plate. Peel the removable serial number label from each Enphase Microinverter and affix it to
the respective location on the Enphase installation map (see map on page 40). Remember to
keep a copy of the installation map for your records.
b. Draw a top-down view of the array using the Array Map template. Make sure to leave enough
room to place the serial number stickers.
c. When installing the microinverters, remove the serial number labels located next to the DC
input cables and place them in the correct order on your drawing of the system. Remember to
keep a copy of the installation map for your records.

Step 12: Connect the PV Modules

WARNING: Electrical shock hazard. The DC conductors of this photovoltaic system are
ungrounded and may be energized.
WARNING: PV modules paired with the M215-60-2LL-S22-IG, S23-IG, or S24-IG must
have DC conductors that are labeled "PV Wire" or "PV Cable" to be compliant with NEC
690.35(D) for Ungrounded PV Power Systems.
NOTE: Completely install all microinverters and all
system AC connections prior to installing the PV
modules.
To connect the modules:
a. Mount compatible PV modules above the microinverters.
b. Mate the microinverters and PV modules as required.
Repeat for all remaining PV modules using one
microinverter for each PV module.
The status LED on the underside of each M215 lights
green six seconds after DC power is applied. It remains
lit solid for two minutes, followed by six green blinks.
After that, red blinks indicate that no grid is present. This
is because the AC breaker is not turned on yet.
24
 2014 Enphase Energy Inc. All rights reserved.
M215 Installation and Operation
http://enphase.com/products/arraygun/
for more
141-00012 Rev 06

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents