enphase IQ Combiner 5 Installing

Hide thumbs Also See for IQ Combiner 5:

Advertisement

Quick Links

Q U I C K I N S T A L L G U I D E
Installing the IQ Combiner 5 and IQ Combiner 5C
The IQ Combiner 5/5C combine up to four AC branch circuits
of IQ Series Microinverters and/or IQ Batteries. To install the IQ
Combiner 5/5C, read and follow all warnings and instructions
in this guide. Safety warnings are listed at the end of this guide.
If you do not fully understand any of the concepts, terminology,
or hazards outlined in these instructions, refer installation to a
qualified electrician or installer. These instructions are not meant
to be a complete explanation of a renewable energy system.
All installations must comply with national and local electrical
codes. Professional installation is recommended.
The IQ Combiner 5/5C have an outdoor-rated, NRTL-certified
NEMA type 3R enclosure containing an IQ Gateway, circuit
breakers, a pair of consumption metering CTs, an IQ Battery
5P metering CT, and wiring for IQ Gateway connections. The IQ
Combiner 5C includes a Mobile Connect LTE-M1 cell modem.
Use the IQ Combiner 5C for single-phase applications and to
support the AC connections needed for an Enphase residential
solar installation.
NOTE: The IQ Combiner 5/5C is compatible with IQ Battery
5P and IQ System Controller 3/3G. It is not compatible with IQ
Battery 3/10/3T/10T and IQ System Controller 1/2.
PREPARATION
NOTE: IQ Combiner 5/5C can be used for grid interactive (i.e., grid-tied) as well as
multi-mode (i.e., grid-forming) installations.
Warning! Risk of equipment damage. Instructions for wiring
grid-forming systems are different from grid-tied systems.
Follow specific wiring instructions as outlined herein to main-
tain warranty.
A ) Download the Enphase Installer App version 3.X mobile app and open it to
log on to your Enphase Installer App account. With this app, you can con-
The information contained in this document is the
nect to the IQ Gateway to track system installation progress. To download,
proprietary and confidential information of ENPHASE
ENERGY, Inc.. You will not provide, make available
or disclose (or use for any purpose other than that
go to https://enphase.com/installers/apps.
contemplated by this document) any such information
to any other party without the express, written consent
of ENPHASE ENERGY, Inc.
B) Check the box for the following items:
• IQ Combiner 5 or 5C with IQ Gateway printed circuit board. The X-IQ-AM1-
240-5C also includes an LTE-M1 cell modem.
• A pair of clamp CTs for consumption metering
• One clamp CT for IQ Battery 5P monitoring
• IQ Combiner 5/5C Quick Install Guide (this document)
C ) Make sure you have the following required items:
• For all Enphase Energy System Installations, a control signal cable is required
and must be purchased separately (for installations with IQ Battery 5P or IQ
System Controller 3), Enphase SKU for control cable: CTRL-SC3-NA-01.
• Tools: Screwdriver, pliers, and torque wrench.
• Up to four Eaton BR-style breakers (one for each PV branch circuit). Eaton
BR-style breakers are the only breakers you can use. You can install upto
60 A breaker(s) in the IQ Combiner (order Enphase BRK-10A-2-240V, BRK-15A-
2-240V, BRK-20A-2P-240V, Eaton BR210, Eaton BR215, Eaton BR220, Eaton
BR230, Eaton BR240, Eaton BR250, and/or Eaton BR260 circuit breakers). The
sum of all distributed energy resources (DER) branch breaker ratings cannot
exceed 80 A. For IQ8 systems with IQ System Controller, use BRK-15A-2P-
240-B(or Eaton BR215B) for 15 A circuits and BRK-20A-2P-240-B(or Eaton
BR220B) for 20 A circuits to be compatible with the hold-down kit. The IQ
Gateway breaker should not exceed 15 A and is counted separately (total
90 A/95 A worth of breakers).
• Up to two hold-down kits with screws for the breakers. Each hold-down kit
(X-IQ-NA-HD-125A) will allow the installation of up to two breakers located on the
same side of the busbar (only for IQ8 PV installations with IQ System Controller).
• Overcurrent protection in the load center in accordance with NFPA
70, 705.12. and NEC 690
• Suitable mounting hardware: Use #8 (or larger) screws that are long enough
to secure the unit to the vertical mounting surface
• Copper conductors rated for wet locations and sized to meet local code
requirements and voltage drop/rise considerations. Wire sizes and torque
values are listed on the door of the unit.
• UL-listed rain-tight conduit hubs for wire entry into the enclosure.
D ) For consumption metering, check that there is enough space in the load
center to install CTs. Do not install the CTs in a panel where they exceed
75% of the wiring space of any cross-sectional area within the load center.
E ) Decide how to connect the IQ Gateway to the internet: Use Wi-Fi and
Enphase Mobile Connect, or Ethernet. Then, make sure you have
NOTES:
the following optional items, if needed:
1. MATERIAL: 3M 7871 POLYESTER BASE MATERIAL,
3M ADHESIVE - 350 HIGH BONDING ACRYLIC ADHESIVE WITH CLEAR OVERLAY ON FRONT.
(Models: X-IQ-AM1-240-5C and X-IQ-AM1-240-5)
380+/-0.3
PRELIMINARY
IMPORTANT: The IQ Gateway inside the IQ Combin-
er is required to monitor the performance of the IQ
Microinverters and to communicate with IQ Battery
5P and IQ System Controller.
Wi-Fi
and
power line
over
line
• Enphase Mobile Connect (included with X-IQ-AM1-240-5C)
• Ethernet cable: 802.3, Cat5E or Cat6, unshielded twisted pair (UTP). Do not use
shielded twisted pair (STP) cable.
When installing with an Enphase Energy System, both Enphase Mobile Connect and
additional internet connection (Wi-Fi or Ethernet) are required.
F ) Make note of the IQ Gateway serial number on the installation map. Later,
you will need to enter this number in Enphase Installer App. You can type it in
manually or scan the label on the inside of the combiner door. Always keep a
copy of the installation map for your records.
G ) Note that installation of the IQ Combiner 5/5C has two parts: To ensure suc-
cessful device detection, complete Part 2 after installing any IQ Microinverter,
IQ Battery 5P, and/or IQ System Controller.
CUT LINE MEASUREMENT
230+/-0.3
GRID-TIED SYSTEMS
IQ Combiner LED & buttons quick reference guide
Enphase Installer Platform (EIP) communication LED
Green when connected to Enphase's EIP cloud.
Flashing green when connecting to EIP or WiFi router.
Red when connected to local network only i.e., no internet.
Off if no network is available
AP mode LED
Green when AP mode is enabled, and IQ Gateway Wi-Fi network is available.
Off when AP mode is disabled.
Off is default unless installer is using AP mode.
AP mode button
Only used by installer during installation or to configure the system.
Starts IQ Gateway's wireless Access Point (AP) to connect mobile phone directly.
Power production LED
Green light when all microinverters are producing power.
Flashing green when an upgrade of the microinverters is in progress.
Red if one or more microinverters stop producing power.
Flashing red when microinverters are not yet detected.
Off if all the microinverters stop producing or communicating.
Usually red at dawn/dusk, off at night & flashing red after IQ Gateway restarts.
Device communication LED
Flashing green when IQ Gateway is scanning for microinverters.
PV CT
Green when all provisioned microinverters are communicating with IQ Gateway.
Red if one or more microinverters are not communicating with IQ Gateway.
Off if all microinverters are not communicating with IQ Gateway.
Usually red during dawn/dusk and off at night.
Device scan button
Only used by installer during installation or to configure the system.
Starts/stops a 15-minute scan for devices over the power line.
All LED' s
Flashing green when software upgrade is in progress.
Flashing red when IQ Gateway is booting up.
On Power-Up, LEDs can take up to 30 seconds to glow.
While restarting, wait for 2 minutes after powering off the IQ Gateway, before powering it back on.
GRID-FORMING SYSTEMS
IQ Combiner 5
Photovoltaic
Combiner Box
X-IQ-AM1-240-5
Electrical ratings
240VAC, 60Hz
Voltage
DG Breakers
80A MAX (combined)
IQ GATEWAY CONTAINS
FCC ID: WS2-WG78DBV0
DG Inputs
64A MAX (combined)
IC ID: 10462A-WG78DBV0
Output
65A MAX, 90A MAX feeder OCPD
CTRL BOARD CONTAINS
Temperature
46°C MAX ambient
FCC ID: MCQ-XBEE3
For DG breaker, use only Eaton BR series.
IC ID: 1846A-XBEE3
P/N:
S/N:
Dedicated solar and DG Combiner Box - do not add loads
10 AMP or 15 AMP IQ Gateway Breaker not used for backfeed
Connection
Wire sizes
Torque
DG Breaker
14-10 AWG
2.2 Nm (20 lb-in)
(1, 2, 3, 4)
8 AWG
2.8 Nm (25 lb-in)
6-4 AWG
3.0 Nm (27 lb-in)
60A Circuit Breaker only
4-1/0 AWG
5.0 Nm (45 lb-in)
IQ Gateway Breaker (5)
14-10 AWG
2.26 Nm (20 lb-in)
IQ Gateway Power Terminals
14-10 AWG
1.4 Nm (12.4 lb-in)
2-1/0 AWG
5.6 Nm (50 lb-in)
P V C T
Large screw
14-3 AWG
5.1 Nm (45 lb-in)
Neutral
6 AWG
3.6 Nm (32 lb-in)
and ground
Small screw
8 AWG
2.6 Nm (23 lb-in)
10-14 AWG
2.3 Nm (20 lb-in)
10-4 AWG
5.0 Nm (45 lb-in)
Main lug
3-2/0 AWG
5.6 Nm (50 lb-in)
18 AWG
0.2 Nm (1.77 lb-in)
CTRL
CTRL Cables (C1,C2)
18 AWG
0.2 Nm (1.77 lb-in)
Connectors
Drain Cables (C3)
Copper conductors only, rated min. 75°C.
Follow NFPA 70 (NEC), or CSA C22.1 part 1, and all local codes.
For DG Breakers larger than 20A, use wire insulated for 90°C
based on 75°C ampacities.
Designed in California and India. Made in Mexico
RECOMMENDED ROUTING
FOR ETHERNET CABLE
IQ Gateway
LOAD CENTER
2
1
CT on IQ Battery L2
CT on consumption L2
CT on consumption L1
CT on PV L1
5
Jumper
3
4
CTRL Board
MAIN
LUG
NA
1 2 3 4
C1
NA
AC
1 2 3 4
C2
NEUTRAL
C3
1 2
TO PV
TO MAIN LOAD CENTER
RECOMMENDED ROUTING
FOR ETHERNET CABLE
IQ Gateway
LOAD CENTER
1
2
CT on IQ Battery L2
CT on consumption L2
CT on consumption L1
5
CT on PV L1
Jumper
To IQ System
Controller 3/3G
3
4
CTRL Board
L1
L2
MAIN
LUG
NA
C1
2
1
3
4
NA
AC
1
2
3
4
C2
NEUTRAL
1 2
C3
WARNING:
TO PV
TO MAIN LOAD CENTER/
- IQ8 Grid-Tied Systems: IQ Gateway must be
powered from IQ Combiner's Breaker
IQ SYSTEM CONTROLLER/
- IQ8 Grid-forming Systems: IQ Gateway must
IQ BATTERY 5P
be powered from IQ System controller
meter
IQ Battery or
Generator
R
REV D
E
01
02
E
03
E
04
E
E
05
P
06
E

Advertisement

loading

Summary of Contents for enphase IQ Combiner 5

  • Page 1 G ) Note that installation of the IQ Combiner 5/5C has two parts: To ensure suc- A ) Download the Enphase Installer App version 3.X mobile app and open it to cessful device detection, complete Part 2 after installing any IQ Microinverter, log on to your Enphase Installer App account.
  • Page 2: Installation - Part

    A ) Install the IQ Combiner 5/5C in a readily accessible location, at least three Refer to the diagram on the door of the IQ Combiner 5/5C and do the follow- feet (91 cm) off the ground.
  • Page 3 NOTE: Consumption metering is mandatory for IQ Battery and Sunlight Backup systems. Battery metering is mandatory for battery systems. The IQ Gateway printed circuit board inside the IQ Combiner 5/5C is pre-wired at the terminal blocks for power and production metering connections. One solid-core Current Transformer (CT) is provided for revenue-grade production metering.
  • Page 4 14-3 AWG 5.1 Nm (45 lb-in) Neutral CTRL H (ORANGE) This section is applicable for Enphase Energy System sites with an IQ System WITH PART NUMBER AND REVISION, MFG CODE AND DATE. 6 AWG 3.6 Nm (32 lb-in) and ground Controller 3/3G and/or IQ Battery 5P installed.
  • Page 5 It is recommended that the drain wire be terminated at the component from which the control wiring for the section is initiated. Same conduits can be used for power and control wire routing only when using Enphase CTRL cable i.e CTRL-SC3-NA-01.
  • Page 6 Last IQ Battery 5P in the daisy chain *Grid-tied system configuration IQ Combiner 5/5C can be used with IQ Battery 5P without an IQ System Controller 3/3G for Grid-tied systems IQ Battery 5P connected to main load center IQ Battery 5P connected to IQ Combiner 5/5C...
  • Page 7 E ) Make sure to tap each device type and scan the power. If you did not use Enphase Installer App, it lights solid green if all devices using the camera scanner. You can also communicating microinverters are producing power.
  • Page 8 On most routers, a WPS indicator begins flashing. • Link B) If you are using the Enphase Installer App, go to your system and tap Enphase • Signal Installer App Step 4 (IQ Gateway connectivity), tap Wi-Fi, and then tap your network from the list of available networks.
  • Page 9: Troubleshooting

    Software upgrade in progress Solid green Communicating with the Enphase Installer Platform Flashing green WPS connection in progress, or IQ Gateway is attempting to connect to Enphase Installer Platform Network communications Solid red Local network connection only No network connection...
  • Page 10: Regulatory Notices

    Mounting rail and rivets Enphase Mobile Connect dimensions REGULATORY NOTICES Le présent appareil est conforme aux CNR d’Industrie Canada applicables aux appareils radio exempts de licence. (Model X-IQ-AM1-240-5C only) L’exploitation est autorisée aux deux conditions suivantes: 1. l’appareil ne doit pas produire de brouillage, et FCC - Antenna - wireless products only 2.
  • Page 11 ELECTRONIC DEVICE: DO NOT THROW AWAY. Waste electrical prod- ucts should not be disposed of with household waste. Refer to your local codes for disposal requirements. © 2023 Enphase Energy. All rights reserved. Enphase, the e and CC logos, IQ, and cer- tain other marks listed at https://enphase.com/trademark-usage-guidelines are trade- marks of Enphase Energy, Inc.
  • Page 12 D E S C R I P T I O N 140-00254-05 May 2023 Initial release © 2023 Enphase Energy. All rights reserved. Enphase, the e and CC logos, IQ, and cer- tain other marks listed at https://enphase.com/trademark-usage-guidelines are trade- marks of Enphase Energy, Inc.

This manual is also suitable for:

Iq combiner 5c