Figure 165:
Three shots with three initiation lines
If the sequence is initiated from the INIT_1 line, that is, the overcurrent protection high
stage, the sequence is one shot long. On the other hand, if the sequence is initiated from
the INIT_2 or INIT_3 lines, the sequence is two shots long.
Table 296:
Settings for configuration example 2
Setting name
Shot number CBB1
Init signals CBB1
First reclose time
Shot number CBB2
Init signals CBB2
Second reclose time
Shot number CBB3
Init signals CBB3
Third reclose time
Control functions
Setting value
1
1 (line 1)
1.0s (an example)
1
6 (lines 2 and 3 = 2+4 = 6)
0.2s (an example)
2
6 (lines 2 and 3 = 2+4 = 6)
10.0s