ABB RER620 Technical Manual page 97

Advanced recloser protection and control
Hide thumbs Also See for RER620:
Table of Contents

Advertisement

1MAC309294-MB F
RER620
Technical Manual
Table 105:
Proposed functionality of numerical transformer and busbar overcurrent protection. DT = definite
time, IDMT = inverse definite minimum time
O/C-stage
Operating char.
HV/51P
DT/IDMT
HV/50P-1/2
DT
HV/50P-3
DT
LV/51P
DT/IDMT
LV/50P-1/2
DT
LV/50P-3
DT
In case the bus-tie breaker is open, the operating time of the blockable overcurrent
protection is approximately 100 ms (relaying time). When the bus-tie breaker is closed,
that is, the fault current flows to the faulted section of the busbar from two directions, the
operation time becomes as follows: first the bus-tie relay unit trips the tie breaker in the
above 100 ms, which reduces the fault current to a half. After this the incoming feeder
relay unit of the faulted bus section trips the breaker in approximately 250 ms (relaying
time), which becomes the total fault clearing time in this case.
Figure 37:
Numerical overcurrent protection functionality for a typical
sub-transmission/distribution substation (feeder protection not shown).
Blocking output = digital output signal from the start of a protection stage,
Blocking in = digital input signal to block the operation of a protection
stage
The operating times of the time selective stages are very short, because the grading
margins between successive protection stages can be kept short. This is mainly due to the
advanced measuring principle allowing a certain degree of CT saturation, good operating
accuracy and short retardation times of the numerical units. So, for example, a grading
Selectivity mode
Operation speed
time selective
low
blockable/time
high/low
selective
current selective
very high
time selective
low
time selective
low
blockable
high
Section 4
Protection functions
Sensitivity
very high
high
low
very high
high
high
91