Chapter 4 Connection and Settings
4.4 Connecting to the Server UPS Unit
CAUTION
4.4.1
Connecting the Server UPS Unit to the Power Synchronized Unit
This section describes the procedure for connecting a power synchronized unit to a server UPS unit with the
power cord (for AC sensor).
Power cords (for AC sensor) must be obtained by customers.
Procedure
1
Connect the power cords (for AC sensor) to the power synchronized unit.
1-1
Connect the plugs of the power cords (for AC sensor) to SENSOR#0 port and SENSOR#1 port on the
power synchronized unit.
FUJITSU Storage ETERNUS DX, ETERNUS AF Configuration Guide (Power Synchronized Unit)
Do
•
When connecting external (signal, power, etc.) cables, avoid placing stress on
them. Not doing so may damage the cables.
Do Not
•
Do not forcibly bend or fold the cable. Doing so may damage the cable and
cause the power synchronized unit to malfunction.
90
Do not bend
more than 90 degrees
Power cord
(for AC sensor)
SENSOR#0 port
Copyright 2017 FUJITSU LIMITED
Do not fold
SENSOR#1 port
57
P3AM-8012-10ENZ0