5 Electrical Connection

5.2 Terminals Description

All electrical terminals are located at the bottom of the inverter. Fig. 5-2 shows the
connection area.
Enough space around the inverter should be kept for electrical
connection when choosing the installation site.
Item
Description
1
Integrated DC switch
2
DC connectors: MC4
3
AC connection terminal
4
Wi-Fi connection terminal
5
DI connection terminal
6
RS485 connection terminal
7
NET connection terminal
8
Second PE terminal

5.3 Meter Connection (optional)

The smart energy meter is installed between the air breaker and the grid. It
measures the feed-in power and communicates with the inverter through RS485
connection. This section describes the power cables connection of the meter.
The following figure shows the cable requirements and connection.
26
1
2
4
6
7
Fig. 5-2 Terminals Description
3
User Manual
5
8

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sg5ktl-ecSg6ktl-ecSg4ktl-ec

Table of Contents