DUT settling time: Time between applying the measurement signal and starting to measure at the
receiver. A DUT settling time is needed if the DUT introduces a significant time delay before the
output reaches its final reaction to the input stimulus.
Attenuator 1 and Attenuator 2: Select the input attenuators.
Reference switch: Receiver 1 and Receiver 2 can be connected either internally or externally
depending on the measurement mode.
Termination switch: When switched on, the Channel 1 and Channel 2 inputs are terminated with
50 Ω. If the switch is open, the input impedance is 1 MΩ.
Probe 1 and Probe 2: Some measurement modes allow you to manually enter a probe factor. For
more details on using probes see
OMICRON Lab
9.8 Using probes
on page 120.