Installing the Chassis
Procedure
Step 1
Install the divider bracket between the left and right cable management frames as follows:
a) Position the divider bracket at the bottom of the left and right middle cable management frames (at the
bottom of the supervisor and I/O module area of the chassis) so that the two screw holes in each side of
the bracket align to two screw holes at the bottom of the left and right middle cable management frames
(see the following figure).
Four screw holes on the upper back of the bracket should also align to four screw holes in the chassis.
Figure 20: Installing the Divider Bracket
1
b) Screw in eight M4 x 13 mm screws to hold this bracket to the bottom of the left middle cable management
bracket (two screws), the bottom of the right middle cable management bracket (two screws), and the
chassis (four screws). Tighten each screw to 11.5 to 15 in-lbs (1.3 to 1.7 N·m).
Step 2
If you also have an air filter kit, install six air filters on the front doors and cable management frames as
explained in
Step 3
Install the door-stop bracket on the top hood of the cable management frames as follows:
a) Position the door-stop bracket under the top hood frame so that its two screw holes align to two screw
holes in the top hood (see the following figure).
Be sure that there is a perpendicular edge facing the front. This edge stops the front doors and provides a
metallic surface for the magnets in the door to hold onto when closed.
Figure 21: Installing the Door-Stop Bracket
1
2
b) Screw in two M4 x 13 mm screws to hold this bracket to the top hood. Tighten each screw to 11.5 to 15
in-lbs (1.3 to 1.7 N·m).
Step 4
Install the two front doors to the supervisor and I/O module area as follows:
OL-30453-01
Position the divider bracket at the bottom of
the middle cable management frame and align
eight screw holes in the bracket to eight screw
holes in the cable management frames (two
holes in each frame) and chassis (4 holes in the
chassis).
Installing the Air Filters, on page 48
Top hood frame with two screw holes on its
bottom side
Door-stop bracket with two screw holes.
Cisco Nexus 7718 Switch Site Preparation and Hardware Installation Guide
Installing the Front Doors
2
Fasten the bracket to the cable management
frames and chassis with eight M4 x 13 mm
screws. Tighten each screw to 11.5 to 15 in-lbs
(1.3 to 1.7 N·m).
3
Align the two screw holes in the bracket with
two screw holes in the top hood. Fasten with
two M4 x 13 mm screws.