CAUTION
KEEP IMPORTANT 5 POINTS FOR PIPING WORK
(1) Take away dust and moisture (Inside of the
connecting pipes.)
(2) Tight the connection (between pipes and unit)
(3) Evacuate the air in the connecting pipes using
a VACUUM PUMP.
(4) Check gas leak (connected points)
(5) Be sure to fully open the packed valves
before operation.
<Packed valve handling precautions>
• Open the valve stem all the way out, but do not try
to open it beyond the stopper.
Pipe size of Packed Valve
12.70 mm and smallers
15.88 mm
• Securely tighten the valve cap with torque in the
following table
Cap
Cap Size (H)
H17 - H19
Valve Rod
Cap
H22 - H30
H14
Service
Port Cap
H17
Service Port Cap
Fig. 10-4-5
Size of Hexagon wrench
A = 4 mm
A = 5 mm
Torque
14~18 N.m
(1.4 to 1.8 kgf·m)
33~42 N.m
(3.3 to 4.2 kgf·m)
8~12 N.m
(0.8 to 1.2 kgf·m)
14~18 N.m
(1.4 to 1.8 kgf·m)
Hexagon wrench
is required.
A
H
Valve Rod Cap
- 70 -
FILE NO. SVM-15058