Equipment and cable installation
............................................................................................................................................................................................................................................................
Power cable and cable bracket installation
Description
This section provides instructions on installing the power cable and cable bracket for the
Alcatel-Lucent 1665 DMX High-Capacity shelf.
Note:
(BDFB) or battery distribution circuit breaker bay (BDCBB) to the Alcatel-Lucent
1665 DMX bay.
Table 1-3, "Power cable assemblies" (p. 1-25)
(p. 1-26)
Procedure
Proceed as follows:
........................................................................................................................................................................................................................
1
Install cable brackets (two per Alcatel-Lucent 1665 DMX High-Capacity shelf, 1 on each
side) as shown in
............................................................................................................................................................................................................................................................
1 - 1 6
Two feeders (A and B) are required from the battery distribution fuse board
list the available power cable assemblies and power connections, respectively.
CAUTION
Verify that the BDCBB breakers are off or that the BDFB fuses are not
installed.
Figure 1-6, "Cable brackets" (p.
Power cable and cable bracket installation
and
Table 1-4, "Power connections"
1-17).
365-372-304R7.1