When shutdown is imminent, the Self Test indicator flashes. These
warnings are approximate, and the actual time to shutdown may vary
significantly. For approximate battery times see the tables on pages 5
and 6. Once these warnings are indicated, immediately complete and
save your work to prevent data loss and similar difficulties. When utility
power is restored after the UPS shuts down, the UPS automatically
connects to the load when the startup is complete.

Diagnostics

The UPS periodically performs diagnostic tests while the unit is
operating in Normal mode, ensuring proper operation. These tests
include:
:
:
:
:
:
The UPS also runs a series of over 20 internal tests when power is first
applied. If a diagnostic test fails, see Chapter 7, "Troubleshooting" on
page 73.

Battery Test on Demand

You can perform a battery test on the UPS while it is operating in
Normal mode by pressing the Output On button. The UPS
automatically distributes some of the load to the batteries for 30 seconds
and tests the battery's performance.
52
Powerware
®
Prestige Series Installation and Operator's Manual for IBM Applications (650 VA - 1500 VA) Uncontrolled Copy
Self Test
Site Fault Test
Utility Verification Test
Battery Discharge Test
Over Temperature Test