Access Power Solutions
Installation and Operation Guide
(APS6-600 Series)
Issue: IPN 997-00012-10A2
Issue Date: July 2018
Refer to the separate SC300 system controller handbook for full details of
the system controller operation.
Eaton Corporation
Telecommunications Power Solutions
dcpower.eaton.com
DCinfo@eaton.com

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the APS6-600 Series and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Eaton APS6-600 Series

  • Page 1 Access Power Solutions Installation and Operation Guide (APS6-600 Series) Issue: IPN 997-00012-10A2 Issue Date: July 2018 Refer to the separate SC300 system controller handbook for full details of the system controller operation. Eaton Corporation Telecommunications Power Solutions dcpower.eaton.com DCinfo@eaton.com...
  • Page 2 In no event will Eaton be responsible to the purchaser or user in contract, in tort (including negligence), strict liability or otherwise for any special, indirect, incidental or consequential damage or loss whatsoever, including but not...
  • Page 3: About This Guide

    Please use this email address to report any problems you find in this guide: Eaton DC Product Marketing Communications EMAIL: DCMarketingNZ@eaton.com For Further Information and Technical Assistance For further information and technical assistance see Worldwide Support on page 103. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 5: Table Of Contents

    Task 4 - Configuring the DC Power System ............... 34 Task 4 - Configuring the DC Power System ............... 34 Task 5 - Applying DC Power to Battery and Load ............35 Start-Up Completed ....................... 36 Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 6 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) System Controller .......................... 37 Configuration File ........................37 Backup and Restore ........................37 Starting the SC300 ........................39 SC300 Operation using the Keypad and Screen ..............39 Keypad Access Security ........................ 39 Alarm Indicators ..........................
  • Page 7: General Description

    Chapter 1 General Description Gener al D escription Overview Topic Page Model Numbers Access Power Solutions DC Power Systems Rectifiers System Controller Input/Output Board Other Features Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 8: Model Numbers

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Model Numbers Model Number DC Output Power (max.) System Controller LVDs (48V nominal) APS6-630 17.28kW SC300 APS6-631 17.28kW SC300 APS6-632 17.28kW SC300 Access Power Solutions DC Power Systems APS6 Models Front View ...
  • Page 9: Aps6 Models Rear View

    MCB positions 9-16 are for high priority loads. For more details see Low Voltage Disconnect Option on page 9. Optional 19" rack mount top cover (IPN 621-08917-15) not shown. AC supply cord(s) may be pre-fitted. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 10: Rectifiers

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Rectifiers Access Power Solutions APS6-600 models can be fitted with 48V Access Power Rectifiers (NPR48-ES). All rectifiers are fan-cooled and hot-pluggable.  See Specifications on page for further information.
  • Page 11: System Controller

    DCTools Configuration Software. Latest version is available free from • dcpower.eaton.com/downloads. PowerManagerII Remote Control and Monitoring Software. Contact your Eaton dc product • supplier for further information (see Worldwide Support on page 103). Recommended web browsers: Microsoft Internet Explorer 11 or later (IE6 is compatible but •...
  • Page 12: Input/Output Board

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Input/Output Board The Input / Output (I/O) board provides the I/O interfaces and connections for the SC300 system controller. The I/O board includes a range of sense inputs for dc power system control and monitoring. It also allows real time data collection from building services and other external devices, and relay outputs for alarm signals or control of external devices.
  • Page 13 LED (green)  Power/Comms OK LED (green)  LVD contactor 1 connector (XH4) and status LED (green)  See Troubleshooting on page for details of I/O board LED signals. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 14: Connections

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Connections The following diagram shows the connections between the SC300, the I/O board, the other dc power system components and external devices.   SC300 system controller Connection to dc live bus ...
  • Page 15: Other Features

    Low Voltage Disconnect Options Single or dual optional Low Voltage Disconnects (LVD) are available for the Access Power Solutions (APS6-600 Series). See the diagram on page for location. These are connected as a battery disconnect (single LVD) or low priority load/battery disconnect (dual LVD).
  • Page 16: Battery Time Remaining

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Battery Time Remaining The SC300 obtains characterization data from a special characterisation discharge test. During a battery discharge, the SC300 uses this characterization data to calculate an estimated time until the battery will reach the specified end voltage.
  • Page 17: Preparation

    Chapter 2 Preparation Prepar ation Overview Topic Page Warnings Inspecting the Equipment and Reporting Damage Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 18: Warnings

     Electrical Safety • Access Power Solutions (APS6-600 Series) dc power systems must be mounted in an enclosed cabinet that meets safety and fire enclosure requirements as specified in AS/NZS 60950.1 and EN 60950-1. • The dc power system may be powered from multiple ac sources. All ac sources must be isolated before internally servicing the equipment.
  • Page 19  Batteries • The plastic cases of batteries installed in Eaton dc power system racks must have a flammability rating of UL 94-V2 or better. • Flooded cell and VRLA lead acid batteries can emit explosive gases and must be installed with adequate ventilation.
  • Page 20: Inspecting The Equipment And Reporting Damage

    Servicing. Servicing must only be performed according to specific instructions and only by personnel authorized by Eaton. This includes disassembly and/or servicing of any modules. • For further information on Servicing contact your local Eaton dc product supplier, or refer to the contact details on page 103. ...
  • Page 21: Installation

    Task 8 - Connect External Input/Output Cabling (if required) Task 9 - Connect Additional Input/Output (if required - SC300 only) Task 10 - Connect to the AC Supply Point Installation Completed Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 22: Installation Tasks

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Installation Tasks Before starting the installation, review the following information: Required Equipment and Tools on page • Warnings and Cautions on page • Inspecting the Equipment and Reporting Damage on page •...
  • Page 23 If necessary, install higher rated RCD(s).  The maximum earth leakage current of Access Power Rectifiers is given in the Specifications on page 71. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 24 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 4 - Check ac discrimination Each rectifier has two internal fast-acting fuses. Under certain internal fault conditions these fuses will blow. If there is insufficient discrimination between these fuses and any upstream ac supply-disconnect device then the upstream ac supply-disconnect device will operate before a rectifier fuse blows.
  • Page 25: Task 2 - Prepare Aps

    If the polarity of the APS is not correct for the equipment to be powered then contact your Eaton dc product supplier for advice (see Worldwide Support on page 103). Step 3 - Check position of mounting brackets APSs are pre-assembled with 19-inch rack-mounting brackets as shown in the following diagram.
  • Page 26 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers)   Rack-mounting bracket (available for 19-inch Alternative bracket mounting positions and 23-inch wide racks) Step 4 - Install Load circuit breakers (if required) Ignore this Step if the load MCBs are already fitted.
  • Page 27 If the arrangement of the ac and dc earths is as required, no further action is required. If the arrangement of the ac and dc earths is not as required, follow the procedure in Earth Bonding on page 87. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 28: Task 3 - Connect The Ac Supply Cable(S)

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers)  Busbar chassis screw  Busbar  Busbar nut  DC common bar Procedure complete Task 3 - Connect the AC Supply Cable(s) Ignore this task if the APS has pre-fitted ac cord(s).
  • Page 29 If the ac supply is 1-phase or 2-phase (L1/L2) then loop together the three live (L) terminal blocks. Connect the phase conductor(s) and the neutral conductor (if fitted) to the terminal block.  Connect according to the labels fitted to the terminal blocks. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 30: Task 4 - Mount The Aps In The Rack

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 7 - Check terminations, secure cables and test insulation Check all terminations are correct and are tightened. Tighten the ac cable entry gland to ensure there is no strain on the terminals.
  • Page 31: Task 5 - Connect The Dc Load And Battery Cables

    Terminate the battery live cable(s) at the battery MCB(s). Tighten the terminals.  The current rating of the MCBs must be derated to 75%. Switch OFF all MCBs. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 32: Task 6 - Install The Batteries

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 4 - Connect load cables Select load cable to suit the dc load currents and voltage drop requirements. Also refer to the table of minimum cable sizes for specific MCBs on page 75.
  • Page 33: Task 7 - Mount The Battery Temperature Sensor

     The Mid-point Monitoring sense wires must have short-circuit protection fitted close to the battery terminals. Use the Battery Mid-point Monitoring kits from Eaton (see Spare Parts on page 68) or equivalent. Connect a Mid-point Monitoring sense wire to the middle interconnecting link on each string of batteries (see following diagram).
  • Page 34: Task 8 - Connect External Input/Output Cabling (If Required)

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 2 - Fix sensor Fix the sensor above the batteries. To avoid false readings: Do not attach the sensor to a battery case, battery cables, terminals or •...
  • Page 35: Task 9 - Connect Additional Input/Output (If Required)

    Task 10 - Connect to the AC Supply Point • A suitably qualified electrician familiar with local wiring regulations must carry out the ac  connection. Step 1 - Replace all covers on the APS Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 36: Installation Completed

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 2 - Connect at the ac supply point Check the ac supply point is isolated. Connect the cord(s) or cable to the ac supply point, or fit plug(s) to the cord(s) to match the wall receptacle/socket(s), as required.
  • Page 37: Start-Up

    Task 2 - Pre-Power-Up Checklist Task 3 - Applying AC Power Task 4 - Configuring the DC Power System Task 5 - Applying DC Power to Battery and Load Start-Up Completed Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 38: Start-Up Tasks

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Start-Up Tasks Complete all the Installation tasks (see details on page 16) before starting these Start-Up tasks. Complete the Start-Up tasks in the following order: Task Description Reference...
  • Page 39: Task 2 - Pre-Power-Up Checklist

    The SC300 system controller will turn on (green Power On LED is on) when the rectifiers • start. During start-up of the system controller the rectifier yellow alarm LEDs will flash until • the rectifiers are registered. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 40: Task 4 - Configuring The Dc Power System

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) After start-up of the system controller: Press any key on the system controller to silence the alarm. •  Depending on the configuration file settings, one or both alarm LED(s) may be on and the system controller may display some system alarm messages.
  • Page 41: Task 5 - Applying Dc Power To Battery And Load

    Step 3 - Connect load Switch on the Load MCB(s) and/or fit the Load fuses. Check the equipment powers up and the Load Fuse Fail alarm clears. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 42: Start-Up Completed

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 4 - Check the rectifier currents Check the rectifier currents. Verify the load current is as expected for the load and battery size and does not exceed the maximum load rating (see details on page 72).
  • Page 43: System Controller

    In DCTools go to File > ICE Backup/Restore and follow the prompts.  The saved file does not include site specific settings including Site Identity, IP Address, S3P Address, battery characterization data. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 44 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) ► To use a web browser for Backup Connect to the SC300 via a web browser. For details see Ethernet Communications in the System Controller Operation Handbook. Go to Tools.
  • Page 45: Starting The Sc300

    Keypad access is Read Only, or PIN Protected and the keypad access PIN is lost. The SC300 will continue to function, but no configuration changes can be made. Contact your Eaton dc product supplier or Eaton for advice (see Worldwide Support on page 103).
  • Page 46: Alarm Indicators

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) ► To use DCTools/Web to enable/disable keypad access In DCTools/Web go to Communications > Front Panel. • Set Access to: • Unprotected - keypad access is allowed to view and change parameters, or •...
  • Page 47: Sc300 Operation Using A Pc/Laptop

    When Disabled, the audible indicator will still indicate an invalid key press. SC300 Operation Using a PC/Laptop DCTools is configuration software for editing a system controller's configuration file (on-line) and monitoring the operation of Eaton's dc power systems. It is available free from dcpower.eaton.com/downloads. Using DCTools via USB DCTools can be run on a PC/laptop connected to the SC300's USB port.
  • Page 48: Sc300 Identity Information

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) SC300 Identity Information The following identity information is stored in the SC300. Parameter Description Where to find: Serial Number The SC300 serial number (factory set). SC300: Info Web:...
  • Page 49 A name that can be entered for the Name configuration file. This name is automatically loaded if the user selects a Generic System Type, or when a configuration file is loaded from web or DCTools. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 50 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) The following configuration information is automatically stored by the SC300: Parameter Description Where to find: Master The name of the configuration file that Configuration was last loaded into the SC300 by web interface or DCTools.
  • Page 51: Generic System Types

    Set for 1 LVD only. EPS 48V LVD Loads a standard 48V positive earth settings. Includes an LVD. EPS48V Loads a standard 48V positive earth settings. No LVD. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 52 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Configuration item: Parameter Description Where to find: Generic System If a suitable configuration file is not Type available, select the appropriate Web: Identity > Software system type here. This will load DCTools: suitable settings into the SC300.
  • Page 53: Maintenance

    Eaton. This includes disassembly and/or servicing of any modules. • For further information on Servicing contact your local Eaton dc product supplier, or refer to the contact details on page 103. Topic Page...
  • Page 54: Troubleshooting

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Troubleshooting Use the table to troubleshoot minor installation and operational problems. For additional assistance see contact details on page 103. Return items for replacement or repair with a completed Equipment Incident Report on page 100.
  • Page 55 Install additional rectifiers. and rectifier yellow LEDs are capacity. on (rectifiers are in current Battery is recharging after ac Check battery has recharged within limit). supply failure. expected time. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 56 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Problem Possible Cause Required Action High system output voltage. Temperature Compensation is None. This is normal operation (if active and the battery batteries are connected). Disable temperature is below the Temperature Compensation if no reference temperature.
  • Page 57: System Controller Problems

    Problem with power or Check all connections (see Connections communications to I/O board. on page 8). SC300 or I/O board software Replace faulty unit. corrupt or hardware fault. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 58 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Problem Possible Cause Required Action Incorrect battery or load Bus voltage sense polarity is Check the bus voltage sense polarity and current readings. incorrect. correct if necessary. Incorrectly configured shunt Check shunt mapping and gain is correct.
  • Page 59 Check S3P Access is enabled. See details in are disabled. the System Controller Operation Handbook. Password required to change See Write Access Password in the System settings (using DCTools or Controller Operation Handbook. PowerManagerII). Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 60 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Problem Possible Cause Required Action Web communications Ethernet communications See previous entry. problem problem. Cannot connect to web server. Check IP address and other settings in SC300 are correct. Check correct IP address is used in web browser address bar.
  • Page 61 I/O board. See details in the System Controller Operation Handbook. Contactor is disconnected. Check the control and dc power cables are connected. See details on page 8. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 62: Replacing Or Adding A Rectifier

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Replacing or Adding a Rectifier Rectifiers can be replaced without switching off the dc power system and disconnecting the equipment it powers. • To reduce the risk of electric shock and maintain optimum system cooling, always cover ...
  • Page 63 Check that the rectifier’s Power On LED turns on (after the startup delay) and the alarm LEDs turn off.  The rectifier will automatically register with the system controller and download its operating parameters. No adjustments are required. Procedure complete Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 64: Replacing Or Adding A Load Mcb

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Replacing or Adding a Load MCB Step 1 - Remove covers Remove the top cover, if fitted. Remove the DC Distribution front cover. Step 2 - Remove existing MCB (if required) Disconnect the load cable and the fuse fail detect wire from the MCB top terminal.
  • Page 65: Replacing The System Controller

    • contact your Eaton dc power system supplier to obtain a master configuration file to suit • the dc power system. This file will have to be customized for the site.
  • Page 66 See Backup and Restore in the System Controller Operation Handbook.  If you receive an error message about the MIB file version, please contact your Eaton dc product supplier for advice, or use a web connection for the backup/restore operation.
  • Page 67: Replacing The Input/Output Board

    One M8 bolt, nut, spring washer, 2 x flat washers and one M6 bolt, nut, spring washer, 2 x • flat washers. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 68 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 1 - Remove top cover (if fitted) Step 2 - Bridge load disconnect LVD (if fitted) Ignore this step if there is no load disconnect LVD fitted.
  • Page 69 When start-up is complete check that the system controller has registered all rectifiers.  Missing Hardware, New Hardware and other alarms will appear because of the I/O board mapping change. Press any key to silence the alarm. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 70 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 7 - Update I/O board mapping  Ignore this step if only one IO Board is fitted. The procedure is automatic for a single IO Board. In DCTools/Web go to: RXP.
  • Page 71: Battery Mid-Point Monitoring (String Fail) Alarm

    Please remember that the owner is responsible and liable to ensure those EPA guidelines or equivalent local regulations are followed. For assistance contact your local hazardous waste facility or Worldwide Support on page 103. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 73: Safety Equipment

    USB port • DCTools software (download from dcpower.eaton.com/downloads). • Test load (to suit maximum output of dc power system) • Labelling tool and labels • Clamp-on ammeter • Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 74: Spare Parts

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Spare Parts Item Description Part Number Rectifier 50V, 3kW: Eaton NPR48-ES See replacement procedure on page 56. Rectifier blank panel Eaton RMB1.5U-00 (to cover un-used rectifier positions) System controller Eaton SC300-00 See replacement procedure on page 59.
  • Page 75: Standard Torque Settings

    When a bolt and nut is torqued use a spanner to prevent rotation. Use hand tools when loosening and tightening stainless steel fasteners. Lubricate bolts before tightening to prevent them locking up. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 77: Specifications

    1P+N+PE (220-240V nom.): 108A (per phase @ V = 175V) 2P+PE (208V nom.): 108A 3P+N+PE (220-240V nom.): 3P+PE (208V nom.): Frequency Range 45-66Hz Earth Leakage Current (maximum) 1.3mA per rectifier Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 78 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) System Output Output Voltage (nominal) 54.5V Dependent on rectifier model. Output Voltage Range 43.2 - 58.0V Output Power (maximum) 18kW* @ 50V Load Current (maximum) Total Load 360A...
  • Page 79 3 (one used for internal current shunt) Range –50 to +50mV Resolution <50µV Accuracy ±0.5% at 25°C [77°F], ±1% over rated temperature range Maximum Cable Length 10m (32 feet) Connector RJ45 Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 80 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Battery Mid-point Monitoring Number of Strings Standard: Maximum: 24 (with additional IOBGP I/O boards) Range –35V to +35V Resolution <30mV Accuracy ±0.5% at 25°C [77°F], ±1% over rated temperature...
  • Page 81: Cable Ratings

    Chint, DZ158-125 Series, 100A, Curve 35mm / 1AWG 307-912519-61 Chint, DZ158-125 Series, 125A, Curve 50mm / 0AWG * or local equivalent. Please contact your local Eaton sales office. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 83: Controller Menus

    At each menu screen press Enter to access the associated configuration menu screen(s). These menus have multiple configuration menu screens. See details in the System Controller Operation Handbook. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 84: Connector Pin-Outs

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Connector Pi n-outs System Controller Connector Pin-outs  Connector Type Purpose Description DB9M RS-232 / RS485 Serial • Interface RD (Receive Data) • TD (Transmit Data) • DTR (Data Terminal Ready) •...
  • Page 85: I/O Board (Iobgp-00, -01, 10,11,20,21) Connector Pin-Outs

    Current Input 2 • 0V out • Current Input 3 Common • Current Input 3 • RJ45 Temperature Sense Inputs • Sensor signal is referenced to • live bus. • Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 86 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Connector Type Purpose Description Temp Sense 1+ • Temp Sense 1- • • Temp Sense 2+ • Temp Sense 2- • LVD Power Bus live • Bus common •...
  • Page 87 • System common - protected • YH11/ RJ45 RXP System System Positive 24/48V • YH11A Communications System Positive 24/48V • (IOBGP-10/11 /20/21 only) • RS485-A • RS485-B • Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 88 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Connector Type Purpose Description • System Negative 24/48V • • RJ45 connector pin-outs RJ45 plug pin-outs Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 89: Transient Protection

    Transient Protection Transi ent Protecti on To prevent damage to Eaton Access Power Solutions from lightning and transient over-voltages, structural lightning protection and transient protection must be installed at each site. Transient protection will also protect against other sources of transients, such as: Circuit or grid switching by the power company •...
  • Page 90 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Primary Transient Protection Primary transient protection must be considered at all sites. Eaton recommends primary transient protection on the incoming ac supply either at the main ac switchboard or sub-switchboard.
  • Page 91 2kA. Tertiary Transient Protection Eaton rectifiers are fitted with 6kV/3kA transient protection. This is designed to protect the rectifiers from voltage spikes generated during operation of the upstream transient protection system. Do not install rectifiers without adequate upstream surge protection.
  • Page 93: Earth Bonding

    21). This link prevents these very large voltages from developing and protects the rectifiers from surge related damage. If your installation uses a mesh earth, then Eaton recommends that this factory fitted ac-dc earth link is retained. No further action is required.
  • Page 94 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Step 2 - Remove or replace the ac-dc Earth Link Ignore this Step if the factory fitted ac-dc earth link is used. There are two options if the ac-dc earth link cannot be retained. Either: •...
  • Page 95: Commissioning

    See details on page System Controls See details on page System Alarms See details on page Digital Inputs See details on page Digital Outputs (Relays) See details on page Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 96: Analog Inputs

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Analog Inputs Equipment required: Digital Voltmeter • DC Load bank • DC Current Clamp meter • Trim pot adjustment tool • Thermometer • Test Test procedure Adjustment •...
  • Page 97 As the analog inputs can be configured for many different types of analog signal, tests have not been detailed on this test sheet. User assigned analog inputs are not available on all systems. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 98: System Controls

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) System Controls Equipment Required: DC Load bank • Test Test procedure Adjustment • Apply a load to the power system. Voltage Control None • With DCTools, ensure the bus voltage matches the Target...
  • Page 99 Reduce the system voltage below the LVD Disconnect Operation Voltage Threshold. Note 7 • Wait for the configured Recognition Period. • Ensure the LVD disconnects. • Ensure the SC300 displays an LVD Disconnected alarm Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 100 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Test Test procedure Adjustment • Ensure the I/O board LVD LED is off. • Increase the system voltage above the configured Reconnect Voltage. • Wait for the configured Recognition Period.
  • Page 101: System Alarms

    Turn off the ac MCBs to 2 rectifiers (if fitted). Multiple rectifier fail • The rectifiers will turn off. • Ensure alarm operates. • Remove a rectifier from the system. Rectifier comms lost • Ensure alarm operates. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 102 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Test Test procedure Adjustment • Remove 2 rectifiers from the system. Multiple Rectifier comms lost • Ensure alarm operates. • Turn off the ac to more than 20% of the rectifiers in the Partial AC Fail system.
  • Page 103 Change the AC Frequency Threshold. Note 6 • Ensure alarm operates. • Change the state of the digital input with Engine Run Engine Run Option function. Note 7 • Ensure alarm operates. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 104: Digital Inputs

    Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Notes Ensure Alarm Tracking is disabled. Ensure Temperature Compensation is enabled. If the load is not connected to the load MCBs and if an electronic Fuse Fail detect circuits is...
  • Page 105: Commissioning Completed

    Commissioning Completed Restore the original (backed-up prior to the testing) configuration file. Use DCTools/Web to change any configuration file settings that were noted as incorrect during the Commissioning tests. Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 106: Equipment Incident Report

    Please enter as much information as you can. Send the completed form, together with the item for repair to your nearest authorized service agent. NOTE: Only one fault to be recorded per form. For further information contact your local Eaton dc product supplier or Eaton (see contact details on page 103). Or email: CustomerServiceNZ@eaton.com...
  • Page 107 ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ ______________________________________________________________________________________ SG/03 ISS06 Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 109: Worldwide Support

    Worldwide Support Worldwide Support For product information and a complete listing of worldwide sales offices, visit Eaton's website at: dcpower.eaton.com or email: DCinfo@eaton.com Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 111: Index

    Connection to AC Supply • 22, 29, 33 Battery Fuses • 50 Current Battery Installation • 26 Battery Current • 52 Disposal and Recycling • 65 Load Current • 52 Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 112 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) Rectifier Current • 39 Current Sense • 6, 8, 73 High AC Voltage Protection • 16 Damage (transport) • 14, 32 Input/Output (I/O) Board DC Common Connections to other system components • 8 AC-DC Earth Connection •...
  • Page 113 SiteSure-3G I/O module Problems • See Troubleshooting Connection to APS • 2 Rectifier Alarms • 4, 33 SMS Text Messaging • See GSM Modem Rectifier blank panel • 56 Communications Copyright © 2018 Eaton Corporation. All Rights Reserved. IPN 997-00012-10A2 July 2018...
  • Page 114 Access Power Solutions Installation and Operation Guide (APS6-600 Series for 3kW Rectifiers) SNMP • 9 SNTP • See Internal Clock Software Versions • 5 Sound • See Audible Alarm Indication Specifications • 71 String Fail Alarm • 9, 51, 65 Target Failed to Respond Error •...

This manual is also suitable for:

Aps3 seriesAps6 seriesAps6-630Aps6-631Aps6-632