Operating Instructions

Pipe Cradle Instructions

The pipe cradle assembly consists of 2 pipe
cradles positioned at either side of the platform and
mounted to the guardrails with U-bolts.
a strap
b U-bolts
c pipe cradle mount
d upper platform
railing
54
e pipe cradle
weldment
f
middle platform
railing
g flat washers
3
h
/
-inch nylock nuts
8
Z-135/70
Second Edition · Fourth Printing

Observe and Obey:

Pipe cradles must be installed on the inside of
the platform.
Pipe cradles must not obstruct the platform
controls or the platform entrance.
The bottom of the pipe cradle tube must rest on
the platform floor.
Be sure the platform is level before installing a
pipe cradle.

Pipe Cradle Installation

1 Install a pipe cradle on each side of the
platform. Refer to the illustration on the left.
Make sure the bottom of the pipe cradle tube
rests on the platform floor.
2 Install two U-bolts from the outside of the
platform rails through each pipe cradle mount.
3 Secure each U-bolt with 2 washers and 2 nuts.