Select Datalink Operation/Status from the Online menu.
The Datalink Status dialog box will be displayed. As shown below, the status of various items is displayed.
The communications cycle time and refresh cycle time are updated only when this window is opened or when
the PLC operating status is changed.
4
Select the Run option in the Operation field.
5
Click the Set button.
The data links will start, and the Operational Status box will be displayed.
Stopping Data Links
1
Click the Stop option in the Operation field of the Datalink Status dialog box.
2
Click the Set button.
The data links will be stopped.
Select either the Run or
Stop option and then
click the Set button.
Note: • The data link mode (manual/automatic) and data link operation are determined by the
data link setup at the startup node. With manual setting the links, it is necessary to set,
for the startup node, the data link table and the data link mode (manual setting) in the
DM parameter area. If these are not set correctly, the data links will not start.
• Check the following points before starting the data links.
With manual setting, the appropriate data link table must be set for each node
executing the data links. Data link tables must be deleted for nodes that are not
participating in the data links. Also, even when the correct data link tables are set, make
sure that there will be no effect on the equipment before starting or stopping the data
links.