Checklist for commissioning

Table B-1  Checklist
No.
Work step
1
Check installation location
1.1
Check sufficient lighting
1.2
Check minimum clearances:
side: 1 m
rear: 1 m
top: 0.20 m
2
Prepare & check the base area
2.1
Base area level?
2.2
Base area dry?
2.3
Carrying capacity sufficient for total weight of the dispenser?
2.4
Position of the DC cable gland suitable?
2.5
Check dimensional accuracy of fastening points
Distances at sides: 484 mm
Distances front and rear: 200 mm Height of bolt anchor: 50 mm
2.6
Check adequate openings for introducing power cables
2.7
Minimum clearance of 0.25 m from power cables possible for routing communication, control
and auxiliary cables?
2.8
System ground
3
Prepare cables
3.1
Ensure that cables are disconnected from the power
3.2
Lay the power cable
3.3
Lay the Ethernet cable
3.4
Lay the DC cable
3.5
Lay communication and signal cables at least 0.25 m away from electric power cables
3.6
Cut cables and wires to length
3.7
Remove cable sheath
3.8
Protect cables and wires from environmental influences
4
Goods acceptance
4.1
Check the transport packaging
4.2
Check completeness and correctness of the delivery
4.3
Document and report any damage, deviations, or missing components
4.4
Acknowledgment and confirmation by carrier
5
Transport to base area and prepare for setup
5.1
Transport to the base area
If crane: Mount crane lugs and fasten the hoisting gear
5.2
Remove cable gland plates